Only the Sprint Retrospective is required by Scrum here. Standing up, burndown charts and release planning are optional practices.
Exam Question
Which of the following is required by Scrum? (choose all that apply)
- A. Sprint Retrospective.
- B. Members must stand up at the Daily Scrum.
- C. Sprint Burndown Chart.
- D. Release Planning.
- E. All of the above.
Correct Answer
A. Sprint Retrospective.
Why This Is the Correct Answer
The Sprint Retrospective is one of the five events in the Scrum Guide, along with the Sprint, Sprint Planning, the Daily Scrum and the Sprint Review. Its purpose is to plan ways to increase quality and effectiveness, and the Guide says “The Sprint Retrospective concludes the Sprint.” The other options are practices that teams may choose to use. The Guide sets the Daily Scrum to 15 minutes but says nothing about standing up. It mentions burn-downs only as one of several ways to forecast progress. Release planning is not an event in Scrum at all, since releases happen whenever it makes sense.
Why the Other Options Are Wrong
B. Members must stand up at the Daily Scrum. Standing is a popular habit to keep the meeting short, but Scrum does not require it.
C. Sprint Burndown Chart. Burndowns are an optional forecasting practice. The Guide names them only as an example.
D. Release Planning. Release Planning was removed from the Scrum Guide years ago. Scrum has no required release planning event.
E. All of the above. Since B, C and D are optional, this cannot be correct.
Exam Tip
Know the short list of what Scrum requires: three accountabilities, five events, three artifacts and their commitments. Anything else in a “required” question is a distractor.
Key Takeaways
- The Sprint Retrospective is a required Scrum event.
- Burndowns and standing up are optional practices.
- Release Planning is not a Scrum event.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- How much time is required after a Sprint to prepare for the next Sprint?” (PSM I)
- What is the accountability of the Product Owner during Sprint 0?” (PSM I)
- True or False: A properly functioning Scrum Team will have at least one Release Sprint.
- Which three of the following are timeboxed events in Scrum?” (PSM I)
- What happens if the Scrum Team cannot complete its work by the end of the Sprint?” (PSM I)