Determining the Order of the Product Backlog
The Product Backlog is a key artifact in Scrum, representing the work to be done on the product. The order of items in the Product Backlog is crucial for maximizing the value delivered by the Scrum Team. This article explores a specific exam question about who has the final say on the order of the Product Backlog, providing detailed explanations and insights relevant to the PSM I exam.
Exam Question
Who has the final say on the order of the Product Backlog?
- A. The Stakeholders
- B. The Developers
- C. The Scrum Master
- D. The Product Owner
- E. The CEO
Correct Answer
D. The Product Owner
Explanation
Correct Answer
D. The Product Owner: The Product Owner is accountable for the order of the Product Backlog. This responsibility includes deciding which items to prioritize based on their value, risk, dependencies, and stakeholder input. The Product Owner’s decisions on ordering are crucial for ensuring that the Scrum Team works on the most valuable items first.
Incorrect Answers
A. The Stakeholders: While stakeholders provide valuable input and feedback regarding the Product Backlog, they do not have the authority to decide the order. Their insights help the Product Owner make informed decisions.
B. The Developers: Developers are responsible for executing the work and may provide input on technical dependencies and effort estimates, but they do not have the final say on the order of the Product Backlog.
C. The Scrum Master: The Scrum Master facilitates Scrum events and helps ensure that Scrum practices are followed but does not have authority over the Product Backlog order.
E. The CEO: Although the CEO may have strategic input and can influence the Product Owner’s decisions, the responsibility for ordering the Product Backlog remains with the Product Owner.
Responsibilities in Scrum
- Product Owner: The Product Owner is responsible for maximizing the value of the product by ordering the Product Backlog effectively. They consider stakeholder input, market conditions, and business objectives when making these decisions.
- Scrum Master: The Scrum Master supports the Product Owner by facilitating Scrum events and ensuring that the team follows Scrum practices. They help resolve impediments and coach the team but do not influence the Product Backlog order.
- Developers: Developers provide technical insights and effort estimates that help the Product Owner make informed decisions about the Product Backlog order. They focus on delivering high-quality increments.
Relevance to the PSM I Exam
Understanding the responsibilities related to the Product Backlog is crucial for the PSM I exam. It demonstrates knowledge of Scrum roles and the decision-making processes within the framework. Mastering these concepts is essential for facilitating effective Scrum practices and ensuring clear role definitions.
Key Takeaways
- The Product Owner has the final say on the order of the Product Backlog.
- Stakeholder input, technical insights, and strategic considerations all inform the Product Owner’s decisions.
- Clear role definitions in Scrum are essential for effective collaboration and product development.
Conclusion
The Product Owner plays a critical role in ordering the Product Backlog to maximize value and ensure that the Scrum Team works on the most impactful items. Understanding this responsibility is essential for effective Scrum implementation and success in the PSM I exam.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- The items at the top of the Product Backlog should be analyzed, estimated, and ordered adequately to begin a Sprint. This is referred to as an actionable, or “Ready”, Product Backlog. At the start of the Sprint Planning, select the best description of the Product Backlog items that the Product Owner wants to have done.
- True or False: The Product Owner should have the entire Product Backlog documented in detail before the first Sprint can start?” (PSM I)
- Scrum is based on empiricism. All of its artifacts must be transparent to ensure sufficient accuracy of inspection. How can the Scrum Team maintain the Product Backlog to maximize its transparency?” (PSM I)
- What are two effective ways for the Scrum Team to make non-functional requirements visible?
- If Product Backlog refinement is needed, when is the ideal time for refinement to take place and who should participate?” (PSM I)