Exam Question
Scrum is based on empiricism. All of its artifacts must be transparent to ensure sufficient accuracy of inspection. How can the Scrum Team maintain the Product Backlog to maximize its transparency? (choose the best answer)
- A. The Product Backlog items must be sized such that the highest ordered items are no bigger than a Sprint.
- B. Product Backlog is only updated at the Sprint Review, when both the Scrum Team and the stakeholders are available.
- C. Product Backlog is only updated at a release planning meeting with the stakeholders and the change control board present.
- D. The Product Backlog is continually kept up to date with the most recent insights.
- E. Product Backlog items should hold no more than 8 points of work, which is average in the range of acceptable sizes of 1, 2, 3, 5, 8, and 13.
Correct Answer
D. The Product Backlog is continually kept up to date with the most recent insights.
Why This Is the Correct Answer
The Product Backlog is emergent. It changes whenever the Scrum Team learns something about the product, the market or the users. The Scrum Guide describes refinement as “an ongoing activity to add details, such as a description, order, and size.” If the backlog only reflects what was known at the last Sprint Review or the last release meeting, inspection is based on stale information. The Guide warns that “Low transparency can lead to decisions that diminish value and increase risk.” Keeping it current is what lets the Product Owner and stakeholders make sound decisions at any time.
Why the Other Options Are Wrong
A. Highest ordered items must be no bigger than a Sprint. Items at the top should be small enough to be Done in a Sprint, but that is about readiness, not transparency. On its own it does not keep the backlog accurate.
B. Only updated at the Sprint Review. The Sprint Review is one input, not the only time changes are allowed. Waiting lets the backlog drift from reality.
C. Only updated at a release planning meeting with a change control board. Scrum has no change control board. Formal gates slow learning and keep the backlog out of date.
E. Items hold no more than 8 points. Story points and size caps are not part of Scrum. A size rule says nothing about whether the content is current.
Exam Tip
Watch for the word “only” in Product Backlog questions. Scrum does not restrict when the backlog may change.
Key Takeaways
- The Product Backlog changes as the team learns.
- Refinement is ongoing, not tied to one event.
- Stale information weakens every inspection.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- What are two effective ways for the Scrum Team to make non-functional requirements visible?
- If Product Backlog refinement is needed, when is the ideal time for refinement to take place and who should participate?” (PSM I)
- True of False: When there are multiple teams working on one product, each Scrum Team should have a separate Product Owner.” (PSM I)
- Scrum is based on empiricism. All Scrum artifacts must be transparent to ensure sufficient accuracy of inspection. Which two measures ensure that the Product Backlog is transparent?
- Which best describes the Product Backlog?” (PSM I)