PSM I exam question

Answering: “True or False: The Product Owner should have the entire Product Backlog documented in detail before the first Sprint can start?” (PSM I)

By Hiro TakashimyaUpdated
Studying for the PSM I exam? Try 20 free practice questions first.Start the free quiz →

False. The Product Owner does not need a fully documented Product Backlog before the first Sprint. It only needs enough well-understood items to give the team a valuable first Sprint.

Exam Question

True or False: The Product Owner should have the entire Product Backlog documented in detail before the first Sprint can start?

  • A. True
  • B. False

Correct Answer

B. False

Why This Is the Correct Answer

The Scrum Guide calls the Product Backlog “an emergent, ordered list of what is needed to improve the product.” Emergent means it changes and grows as the team and stakeholders learn. Items near the top get refined into smaller, more precise pieces, while items further down stay rough until they are needed. Writing everything in detail up front wastes effort, because much of that detail will be wrong or irrelevant once real feedback arrives. To start the first Sprint, the Scrum Team only needs enough ready items for Sprint Planning and a Product Goal to work toward.

Why the Other Options Are Wrong

A. True This treats Scrum like a waterfall project with a requirements phase. It delays value and ignores what will be learned from early Increments.

Exam Tip

Any statement that something must be complete, fully detailed or approved before the first Sprint is almost always false in Scrum.

Key Takeaways

  • The Product Backlog is emergent.
  • Only items near the top need detail.
  • The first Sprint needs enough ready work, not a complete backlog.