Estimating Product Backlog Items
Estimating Product Backlog items is a crucial part of Scrum, ensuring that the team can plan and execute their work effectively. This article explores who is responsible for creating these estimates and ensuring they meet the Definition of Done.
Exam Question
Who creates a Product Backlog item’s estimate?
(choose the best answer)
A. The Scrum Master.
B. The most senior people in the organization, including architects and subject matter experts.
C. The Developers after clarifying requirements with the Product Owner.
D. The Developers, alone.
E. The Product Owner with input from the Developers.
Correct Answer
C. The Developers after clarifying requirements with the Product Owner.
Explanation
Correct Answer
C. The Developers after clarifying requirements with the Product Owner:
In Scrum, the Developers are responsible for estimating the effort required to complete Product Backlog items. They create these estimates after clarifying the requirements and understanding the details provided by the Product Owner. This collaborative approach ensures that the estimates are realistic and based on a clear understanding of the work involved. Additionally, the Developers know what it takes to ensure that the item conforms to the Definition of Done, which includes meeting quality standards and any criteria specified by the team.
Incorrect Answers
A. The Scrum Master:
The Scrum Master facilitates the Scrum process and supports the team but does not create estimates. Their role is to ensure that the team follows Scrum practices and helps remove impediments.
B. The most senior people in the organization, including architects and subject matter experts:
While senior people and experts can provide valuable insights and guidance, the actual estimation is done by the Developers who will be doing the work. This ensures that the estimates are based on the team’s understanding and capabilities.
D. The Developers, alone:
While the Developers create the estimates, they do so after clarifying requirements with the Product Owner. This collaboration ensures that the estimates are accurate and aligned with the product goals.
E. The Product Owner with input from the Developers:
The Product Owner does not create the estimates. They provide the necessary information and clarify requirements, but the actual estimation is done by the Developers.
Responsibilities in Scrum
- Product Owner: Provides clear and detailed requirements for the Product Backlog items and collaborates with the Developers to ensure they understand the work.
- Scrum Master: Facilitates the estimation process, ensuring that the team follows Scrum practices and that any impediments are removed.
- Developers: Create the estimates for Product Backlog items based on their understanding of the requirements, the effort involved in completing the work, and ensuring the items conform to the Definition of Done.
Relevance to the PSPO II Exam
Understanding who is responsible for estimating Product Backlog items is crucial for the PSPO II exam. It demonstrates knowledge of team collaboration and the roles and responsibilities within the Scrum framework.
Key Takeaways
- Developers are responsible for creating estimates for Product Backlog items.
- Estimates are created after clarifying requirements with the Product Owner.
- Collaboration between the Product Owner and Developers ensures accurate and realistic estimates.
- Developers ensure that Product Backlog items conform to the Definition of Done.
Conclusion
Estimating Product Backlog items is a collaborative process where Developers create the estimates after clarifying requirements with the Product Owner. This approach ensures that the estimates are realistic, based on a clear understanding of the work involved, and conform to the Definition of Done.

Get ready for the official PSPO II exam
120 PSPO II practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 40 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO II exam fee ($250) is paid separately to Scrum.org.
More PSPO II exam questions
- Which statement best describes the Sprint Review?” (PSPO II)
- If burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate?” (PSPO II)
- Which of the following are characteristics of a Product Goal?
- Which output from Sprint Planning provides the Scrum Team with a target and overarching direction for the Sprint?” (PSPO II)
- As a Product Owner you become aware that the quality assurance criteria, defined in the Definition of Done, were not met for the latest Increment. Which of the following statements are true?