The Product Backlog should be visible to the Scrum Team and stakeholders, and the Product Owner orders it. It does not have to be complete before the first Sprint, use user stories or replace conversations with stakeholders.
Exam Question
Which of the following statements about the Product Backlog are true?
(choose the best two answers)
A. The Product Backlog should be visible to the Scrum Team and stakeholders.
B. All Product Backlog items must be identified before the first Sprint begins.
C. Only the Product Owner can place items on the Product Backlog.
D. The Product Backlog is ordered by the Product Owner.
E. The Product Backlog represents the input of all stakeholders and eliminates any need for the Developers to speak to stakeholders.
F. All Product Backlog items must be expressed as user stories.
Correct Answer
A and D.
Why This Is the Correct Answer
The Scrum Guide says the Product Owner is accountable for “Ensuring that the Product Backlog is transparent, visible and understood” and for ordering Product Backlog items. The Product Owner may delegate some of that work, but remains accountable. Visibility lets stakeholders inspect what is planned and influence it by talking to the Product Owner. Ordering turns the backlog into a clear plan for what comes next. The other statements describe a fixed, document-driven approach. Anyone can suggest items, the backlog keeps emerging, Scrum prescribes no format, and Developers are expected to talk with stakeholders to understand the work.
Why the Other Options Are Wrong
B. All items must be identified before the first Sprint. The Product Backlog is emergent. It grows and changes as the team learns.
C. Only the Product Owner can add items. Anyone can propose items. The Product Owner decides their order and content but does not have to type them all in.
E. The backlog removes the need for Developers to talk to stakeholders. The backlog is a starting point for conversation. Direct collaboration with stakeholders improves understanding.
F. All items must be user stories. User stories are optional. Scrum does not prescribe a format for Product Backlog items.
Exam Tip
Statements with “all,” “only” or “must” about the Product Backlog are usually false. The true ones talk about transparency and ordering.
Key Takeaways
- The Product Backlog is visible to the team and stakeholders.
- The Product Owner is accountable for its order.
- It is emergent and has no required format.

Get ready for the official PSPO II exam
120 PSPO II practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 40 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO II exam fee ($250) is paid separately to Scrum.org.
More PSPO II exam questions
- Which of the following are advantages of a Product Goal that is well-understood by the Scrum Team?
- Your product’s nearest competitor has lower market share, but has higher customer satisfaction, though they lack some key features of your product. You are losing market share to them as customers discover them. They are able to release 3 times faster than you, which is helping them to win customers. What should you do first in response?
- Which of the following statements is true about the Product Vision?
- Choose the two measurements which provide the best indicator to the Product Owner that value is being delivered.
- When should the Sprint Retrospectives be held?