PSPO I exam question

Answering: “The “cone of uncertainty” can be used to do what?”

By Hiro TakashimyaUpdated
Studying for the PSPO I exam? Try 14 free practice questions first.Start the free quiz →

The cone of uncertainty illustrates that the further out a forecast goes, the less certain it becomes. It does not fix project cost up front or justify cutting quality.

Exam Question

The “cone of uncertainty” can be used to do what?
(choose the best answer)

  • A. Determine the cost of a project before it begins.
  • B. Project what will be completed by a given Sprint.
  • C. Determine whether to cut quality, similar to the “Iron Triangle” of project management.
  • D. Illustrate that as a project forecast lengthens, it is increasingly less certain.

Correct Answer

D. Illustrate that as a project forecast lengthens, it is increasingly less certain.

Why This Is the Correct Answer

The cone of uncertainty is drawn as a range that widens over time. Near-term forecasts sit in a narrow band, while long-range forecasts span a much wider one. That picture supports Scrum’s empirical approach. The Scrum Guide notes that in complex environments “what will happen is unknown” and that only what has already happened may be used for forward-looking decisions. Product Owners use the cone to explain to stakeholders why long-term promises are risky and why forecasts are updated each Sprint.

Why the Other Options Are Wrong

A. Determine the cost of a project before it begins. The cone shows that early estimates are the least reliable, so it argues against fixing cost up front.

B. Project exactly what will be completed by a given Sprint. The cone gives a range, not a precise projection. The wider the range, the less exact the answer.

C. Decide whether to cut quality, like the Iron Triangle. Quality does not decrease in Scrum, and the cone is about uncertainty, not trade-offs.

Exam Tip

This question has a PSPO II twin that frames the cone as a scope forecasting aid. In both, the core idea is that uncertainty grows with distance into the future.

Key Takeaways

  • Forecasts get less certain the further out they reach.
  • The cone supports empirical, regularly updated forecasts.
  • It argues against fixing cost or scope up front.
Professional Product Owner PSPO I™ Exam Prep

Get ready for the official PSPO I exam

320 PSPO I practice questions, each with an in-depth explanation like the one above.

  • Practice Mode: study at your own pace and choose the test length.
  • Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.

$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.

More PSPO I exam questions

Practice all 320 PSPO I questions →