The cone of uncertainty illustrates that the further out a forecast goes, the less certain it becomes. It does not fix project cost up front or justify cutting quality.
Exam Question
The “cone of uncertainty” can be used to do what?
(choose the best answer)
- A. Determine the cost of a project before it begins.
- B. Project what will be completed by a given Sprint.
- C. Determine whether to cut quality, similar to the “Iron Triangle” of project management.
- D. Illustrate that as a project forecast lengthens, it is increasingly less certain.
Correct Answer
D. Illustrate that as a project forecast lengthens, it is increasingly less certain.
Why This Is the Correct Answer
The cone of uncertainty is drawn as a range that widens over time. Near-term forecasts sit in a narrow band, while long-range forecasts span a much wider one. That picture supports Scrum’s empirical approach. The Scrum Guide notes that in complex environments “what will happen is unknown” and that only what has already happened may be used for forward-looking decisions. Product Owners use the cone to explain to stakeholders why long-term promises are risky and why forecasts are updated each Sprint.
Why the Other Options Are Wrong
A. Determine the cost of a project before it begins. The cone shows that early estimates are the least reliable, so it argues against fixing cost up front.
B. Project exactly what will be completed by a given Sprint. The cone gives a range, not a precise projection. The wider the range, the less exact the answer.
C. Decide whether to cut quality, like the Iron Triangle. Quality does not decrease in Scrum, and the cone is about uncertainty, not trade-offs.
Exam Tip
This question has a PSPO II twin that frames the cone as a scope forecasting aid. In both, the core idea is that uncertainty grows with distance into the future.
Key Takeaways
- Forecasts get less certain the further out they reach.
- The cone supports empirical, regularly updated forecasts.
- It argues against fixing cost or scope up front.

Get ready for the official PSPO I exam
320 PSPO I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.
More PSPO I exam questions
- Which of the following practices might help the Product Owner minimize waste in developing and sustaining the Product Backlog?” (PSPO I)
- What might indicate to a Product Owner that they need to work more with the Scrum Team?” (PSPO I)
- True or False: Sprint Reviews are an opportunity to collect customer feedback.
- What sources may a Product Owner use when considering the value of a product?
- When should the Product Owner update the project plan?” (PSPO I)