True. The Sprint Review is a natural place to get feedback from customers and other stakeholders on what was built. That feedback shapes what the team does next.
Exam Question
True or False: Sprint Reviews are an opportunity to collect customer feedback.
A. True
B. False
Correct Answer
A. True
Why This Is the Correct Answer
The Scrum Guide says “the purpose of the Sprint Review is to inspect the outcome of the Sprint and determine future adaptations.” It describes the Scrum Team presenting results to key stakeholders, who then work together on what to do next. Customers are often among those stakeholders. Seeing the Increment lets them say what works, what is missing and what has changed in their world. The Product Backlog may then be adjusted to reflect new opportunities. This is why the Guide warns against limiting the Sprint Review to a presentation: it is a working session meant to gather feedback.
Why the Other Options Are Wrong
B. False Collecting stakeholder feedback is part of the Sprint Review’s purpose. Calling it out of scope would turn the event into a one-way demo.
Exam Tip
If a question asks whether the Sprint Review involves feedback, the answer is yes. It is a two-way working session, not a sign-off or a presentation.
Key Takeaways
- The Sprint Review is a working session with stakeholders.
- Customer feedback can reshape the Product Backlog.
- The event inspects the outcome and adapts what comes next.

Get ready for the official PSPO I exam
320 PSPO I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.
More PSPO I exam questions
- What sources may a Product Owner use when considering the value of a product?
- When should the Product Owner update the project plan?” (PSPO I)
- The process of regular inspection and adaptation employs knowledgeable and skilled inspectors. What are two ways in which the Product Owner takes the lead in the inspection process?
- What variables should a Product Owner consider when ordering the Product Backlog?
- If burndown charts are used to visualize progress, what do they track?” (PSPO I)