All five activities are part of managing a Product Backlog. Ordering, forecasting effort, reviewing it with stakeholders, reducing dependencies and splitting large items all help keep it useful.
Exam Question
Managing a Product Backlog involves which of the following activities?
(choose all that apply)
A. Ordering the Product Backlog.
B. Forecasting the effort of Product Backlog items.
C. Reviewing the Product Backlog with stakeholders.
D. Reducing or eliminating dependencies between Product Backlog items.
E. Breaking large Product Backlog items into multiple smaller Product Backlog items.
Correct Answer
A, B, C, D and E.
Why This Is the Correct Answer
The Scrum Guide lists ordering and clearly communicating items among the Product Owner’s accountabilities, along with keeping the Product Backlog “transparent, visible and understood.” Refinement is described as “the act of breaking down and further defining Product Backlog items into smaller more precise items,” which covers splitting large items. Sizing is part of refinement too, and “the Developers who will be doing the work are responsible for the sizing.” Reviewing the backlog with stakeholders keeps it aligned with their needs. Reducing dependencies lets the Product Owner order by value more freely.
Exam Tip
In “choose all that apply” questions about Product Backlog management, check each option against ordering, refining, sizing and transparency. If all fit, select them all.
Key Takeaways
- Managing the Product Backlog includes ordering, refining and sizing.
- Stakeholder review keeps it aligned with real needs.
- Fewer dependencies give more freedom to order by value.

Get ready for the official PSPO II exam
120 PSPO II practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 40 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO II exam fee ($250) is paid separately to Scrum.org.
More PSPO II exam questions
- A user satisfaction gap exists when there is a difference between:” (PSPO II)
- The leading revenue-producing product in your portfolio has:
- The Developers have struggled to get all of their forecasted work done during the last three Sprints. As a Product Owner what steps could you take to help the Developers improve their ability to deliver a done Increment?
- What is the Product Owner responsible for during the Sprint Retrospective?” (PSPO II)
- Product A is a big revenue producer; it has: