The Product Owner can delegate developing and communicating the Product Goal and ordering Product Backlog items, while staying accountable for both. Attending events is not “work” that gets delegated in this sense.
Exam Question
A Product Owner is accountable for maximizing the value of the product that is the result of the work of the Scrum Team. Which of the following can be delegated to others, while the Product Owner remains accountable for the work?
(choose the best two answers)
A. Developing and communicating the Product Goal.
B. Attending the Sprint Review.
C. Attending the Sprint Retrospective.
D. Ordering Product Backlog items.
Correct Answer
A and D.
Why This Is the Correct Answer
The Scrum Guide lists the Product Owner’s Product Backlog management work: developing and explicitly communicating the Product Goal, creating and communicating Product Backlog items, ordering them, and keeping the backlog transparent and understood. It then says: “The Product Owner may do the above work or may delegate the responsibility to others. Regardless, the Product Owner remains accountable.” Both A and D come straight from that list.
Why the Other Options Are Wrong
B. Attending the Sprint Review. The Product Owner is a member of the Scrum Team and takes part in the Sprint Review with the rest of the team and stakeholders. Sending someone else in their place is not delegation of Product Backlog work.
C. Attending the Sprint Retrospective. The Retrospective is for the whole Scrum Team, Product Owner included, to inspect how they work. It is participation, not a task to hand off.
Exam Tip
When the PSPO exam asks what can be delegated, look for the Product Backlog management activities from the Scrum Guide. Accountability itself never moves.
Key Takeaways
- Product Backlog management work can be delegated; accountability cannot.
- The Product Owner takes part in Scrum events as a team member.
- Delegation still needs the Product Owner’s decisions to be respected by the organization.

Get ready for the official PSPO I exam
320 PSPO I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.
More PSPO I exam questions
- The Definition of Done serves which three purposes?” (PSPO I)
- Which statement best describes the Sprint Backlog as the output of the Sprint Planning?” (PSPO I)
- When should a Sprint Goal be created?” (PSPO I)
- A new Developer is having continuing conflicts with existing members of the Scrum Team, which is impacting the delivery of the Increment. If necessary, who is responsible for removing the Developer from the Scrum Team?
- User documentation is part of your Definition of Done. However, there are not enough technical writers for all teams. Your Scrum Team does not have a Technical Writer. What should the Scrum Team do?” (PSPO I)