Answering: “What is a probabilistic forecast intended to communicate?”

What is a probabilistic forecast intended to communicate?
(choose the best answer)
A. A forecast based on past performance that can help discussions about the likelihood of achieving a certain goal in a given time frame.
B. The best way to predict the future performance of a team.
C. A guarantee of when a certain amount of scope will be complete.

Answering: “What is a probabilistic forecast intended to communicate?” Read More »

Answering: “What should the Developers do if, during a Sprint, the Product Owner asks them to add an urgent unplanned work item that aligns to the Sprint Goal but does not fit into the current Work in Progress (WIP) Limits?”

What should the Developers do if, during a Sprint, the Product Owner asks them to add an urgent unplanned work item that aligns to the Sprint Goal but does not fit into the current Work in Progress (WIP) Limits?
(choose the two best answers)
A. Reject the urgent item because the WIP Limits do not allow it. Tell the Product Owner to wait until the next Sprint.
B. Add the urgent item to their Sprint Backlog but only start working on it when their WIP Limits allow it.
C. Take on the urgent item as an exception to the WIP Limits and visualize that they are above their WIP Limit.
D. Adjust the WIP Limits to allow for taking on the extra item and record it as part of their definition of Workflow.

Answering: “What should the Developers do if, during a Sprint, the Product Owner asks them to add an urgent unplanned work item that aligns to the Sprint Goal but does not fit into the current Work in Progress (WIP) Limits?” Read More »

You cannot copy content of this page