Answering: “In which of these situations should the Scrum Team adjust their Work in Progress (WIP) Limits?”
In which of these situations should the Scrum Team adjust their Work in Progress (WIP) Limits?
(choose the best answer)
A. When there is unplanned urgent work that emerges during the Sprint.
B. When they see that the average story size they are working on is growing.
C. When they have extra capacity during the Sprint and want to start some new work items from the Sprint Backlog.
D. When they want to improve their cycle time, flow, and focus.