Answering: “A Product Backlog item has met the Scrum Team’s Definition of Done halfway through the Sprint. The item is especially important to one particular stakeholder, and the Scrum Team decides to show the Increment containing the item to the stakeholder for feedback, rather than wait until the Sprint Review.”
A Product Backlog item has met the Scrum Team’s Definition of Done halfway through the Sprint. The item is especially important to one particular stakeholder, and the Scrum Team decides to show the Increment containing the item to the stakeholder for feedback, rather than wait until the Sprint Review.
How should this discussion be facilitated?
(choose the best answer)
A. The Scrum Master should facilitate the session because they are the expert at facilitation.
B. The Scrum Team should organize a special, formal mid-Sprint Sprint Review that gives all the Scrum Team’s stakeholders the opportunity to attend.
C. Anyone on the Scrum Team can facilitate a session with the stakeholder.
D. This breaks the rules of Scrum – inspection of increments must only happen at the Sprint Review.
E. The Product Owner should have a separate session with the stakeholder so the rest of the Scrum Team can focus on the rest of the Development work in the Sprint.