During the Sprint, a small feature enhancement request that is unrelated to the Sprint Goal is made directly to the Developers by a very influential stakeholder. The stakeholder insists that the item needs to be incorporated into the current Sprint.
The Developers are unsure whether they have the capacity to complete the enhancement without impacting their ability to meet the Sprint Goal. What is the best course of action to take?
(choose the best answer)
A. The Developers should discuss the request with the Product Owner and decide together if they should add the work to the Sprint.
B. The Developers should immediately evaluate the enhancement and determine how much work it will take to complete.
C. The Developers should accept and complete the small enhancement in the current Sprint.
D. The Developers should add the enhancement to the Product Backlog and discuss it in the next Sprint Review.