Answering: “At the end of a Sprint, a Product Backlog item worked on during the Sprint does not meet the Definition of Done. What two things should happen with the undone Product Backlog item?”

At the end of a Sprint, a Product Backlog item worked on during the Sprint does not meet the Definition of Done. What two things should happen with the undone Product Backlog item?
(choose the best two answers)
A. Put it on the Product Backlog for the Product Owner to decide what to do with it.
B. If the stakeholders agree, the Product Owner can accept it and release it to the users.
C. Do not include the item in the Increment this Sprint.
D. Review the item, add the done part of the estimate to the velocity and create a Story for the remaining work.

Answering: “At the end of a Sprint, a Product Backlog item worked on during the Sprint does not meet the Definition of Done. What two things should happen with the undone Product Backlog item?” Read More »

Answering: “UX & Research work in Scrum can be done as part of Product Backlog refinement, and:”

UX & Research work in Scrum can be done as part of Product Backlog refinement, and:
(choose the best two answers)
A. It is the responsibility of the UX Team.
B. It must be rigorously checked against the Definition of Ready.
C. It can also be done as part of the Sprint.
D. It is the responsibility of the Scrum Team.

Answering: “UX & Research work in Scrum can be done as part of Product Backlog refinement, and:” Read More »

Answering: “True of False: The entire Scrum Team works together to build a shared understanding of the customer, their problems, needs, wants, a proposed solution, and desired outcomes.”

True of False: The entire Scrum Team works together to build a shared understanding of the customer, their problems, needs, wants, a proposed solution, and desired outcomes.
A. True
B. False

Answering: “True of False: The entire Scrum Team works together to build a shared understanding of the customer, their problems, needs, wants, a proposed solution, and desired outcomes.” Read More »

Answering: “Which best describes the Product Backlog?”

Which best describes the Product Backlog?
(choose the best answer)
A. It is baselined to follow change management processes.
B. It contains all foreseeable tasks and requirements from which the Scrum Team can develop and maintain a complete project plan.
C. It is allowed to grow and change as more is learned about the product and its customers.
D. It provides just enough information to enable a Scrum Team to start the design phase of a product.

Answering: “Which best describes the Product Backlog?” Read More »