What happens if the Scrum Team cannot complete its work by the end of the Sprint

Answering: “What happens if the Scrum Team cannot complete its work by the end of the Sprint?”

What happens if the Scrum Team cannot complete its work by the end of the Sprint?
(choose the best answer)
A. The Sprint is extended temporarily. Lessons are taken to ensure it doesn’t happen again.
B. The Sprint is extended and future Sprints use this new duration.
C. The Sprint length is unchanged and the Scrum Team continuously learns and adapts.

Answering: “What happens if the Scrum Team cannot complete its work by the end of the Sprint?” Read More »

Which of the following are true about the length of the Sprint

Answering: “Which of the following are true about the length of the Sprint?”

Which of the following are true about the length of the Sprint?
(choose the best answer)
A. All Sprints must be one month or less.
B. The length of the Sprint should be proportional to the work that is done in between Sprints.
C. Sprint length is determined during Sprint Planning, and should be long enough to make sure the Scrum Team can deliver what is to be accomplished in the upcoming Sprint.
D. Sprint length is determined during Sprint Planning, and should hold the time it will take to build the planned features in the upcoming Sprint, but does not include time for any testing.

Answering: “Which of the following are true about the length of the Sprint?” Read More »

How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog

Answering: “How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?”

How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?
(choose the best answer)
A. The Developers pull in work in agreement with the Product Owner.
B. The Product Owner should provide each team with its own Product Backlog.
C. Each Scrum Team takes an equal number of items.
D. The Product Owner decides.
E. The Scrum Team with the highest velocity pulls Product Backlog items first.

Answering: “How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?” Read More »