Answering: “What is the Scrum Master responsible for during the Sprint Retrospective?”

What is the Scrum Master responsible for during the Sprint Retrospective?
(choose the best answer)
A. Acting as a scribe to capture the Scrum Team’s answers.
B. Participating as a Scrum Team member and facilitating as requested or needed.
C. Prioritizing the resulting action items.
D. Summarizing and reporting the discussions to management.

Answering: “What is the Scrum Master responsible for during the Sprint Retrospective?” Read More »

Answering: “What are two ways that architecture and infrastructure are handled in Scrum?”

What are two ways that architecture and infrastructure are handled in Scrum?
(choose the best two answers)
A. They are discussed, determined, and documented before the actual feature development Sprints.
B. They are built by a separate team through the creation of an architectural runway.
C. They are added to the Product Backlog and addressed in early Sprints, while always requiring at least some business functionality, no matter how small.
D. They are implemented along with functional development of the product.

Answering: “What are two ways that architecture and infrastructure are handled in Scrum?” Read More »

Answering: “True or False: To get started in terms of what to build, Scrum requires no more than a Product Owner with enough ideas for a first Sprint, Developers to implement those ideas, and a Scrum Master to help guide the process.”

True or False: To get started in terms of what to build, Scrum requires no more than a Product Owner with enough ideas for a first Sprint, Developers to implement those ideas, and a Scrum Master to help guide the process.
A. True
B. False

Answering: “True or False: To get started in terms of what to build, Scrum requires no more than a Product Owner with enough ideas for a first Sprint, Developers to implement those ideas, and a Scrum Master to help guide the process.” Read More »

Answering: “Who is responsible for the sizing of Product Backlog items?”

Who is responsible for the sizing of Product Backlog items?
(choose the best answer)
A. The Scrum Master.
B. The Developers, alone.
C. The Product Owner with input from the Developers.
D. The most senior people in the organization, including architects and subject matter experts.
E. The Developers after clarifying requirements with the Product Owner.

Answering: “Who is responsible for the sizing of Product Backlog items?” Read More »