To initiate a Scrum project, the essential elements include a Product Owner with a clear vision for the product, Developers to implement the ideas, and a Scrum Master to guide the process.
Exam Question
True or False: To get started in terms of what to build, Scrum requires no more than a Product Owner with enough ideas for a first Sprint, Developers to implement those ideas, and a Scrum Master to help guide the process.
A. True
B. False
Correct Answer
A. True
Explanation
Scrum is designed to be a lightweight framework that can be initiated with minimal setup. The primary requirement is a cross-functional team capable of delivering a potentially shippable product increment within a Sprint.
Correct Answer:
A. True:
This statement accurately reflects the basic requirements to start a Scrum project. Scrum emphasizes starting with what is known and building iteratively.
Why Other Options Are Incorrect
B. False:
This option is incorrect because it suggests that more is needed to get started with Scrum. However, the minimal setup of a Product Owner, Developers, and a Scrum Master is sufficient to begin the iterative process of delivering increments of the product.
Responsibilities in Scrum
- Product Owner: Ensures the Product Backlog is ordered and refined to maximize value and align with the team’s capacity. Develops and explicitly communicates the Product Goal. Creates and clearly communicates Product Backlog items. Represents the needs of many stakeholders in the Product Backlog. Optimizes the value of the work the Scrum Team does by making informed decisions on the Product Backlog.
- Scrum Master: Coaches the team in Scrum practices, removes impediments, and facilitates team events to ensure productivity and adherence to Scrum principles. Helps everyone understand Scrum theory and practice within the Scrum Team and the organization. Ensures that Scrum events are productive and kept within the timebox.
- Developers: Collaborate to create the Sprint Goal and the Sprint Backlog, ensuring all work aligns with the Sprint Goal. Complete all tasks necessary to deliver a potentially shippable Increment, including ensuring that all Product Backlog items meet the Definition of Done.
Relevance to the PSM I Exam
Understanding the fundamental requirements to start a Scrum project is crucial for the PSM I exam. This knowledge emphasizes the simplicity and minimalism of Scrum, focusing on incremental progress and team collaboration.
Key Takeaways
- Minimal Setup: Scrum can be initiated with a minimal setup of a Product Owner, Developers, and a Scrum Master.
- Iterative Progress: Emphasizes starting with known ideas and building iteratively.
- Value Delivery: Focuses on delivering value through small, manageable increments.
Conclusion
Scrum’s simplicity and minimal initial setup make it accessible for teams to start delivering value quickly.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- Which Scrum Values are violated by building Product Backlog Items that have low business value?” (PSM I)
- True or False: Scrum is a methodology that tells in detail how to build software incrementally.
- Which three of the following are true about Scrum?
- Upon what type of process control is Scrum based?
- True or False: A Scrum Team is only allowed to meet with stakeholders during Sprint Review.