Answering: “You are the Scrum Master of a Scrum Team that has one Developer who disagrees with team decisions. Their disagreements are becoming disruptive and slowing progress. The Developer often returns to earlier team decisions and re-opens the issue.”

You are the Scrum Master of a Scrum Team that has one Developer who disagrees with team decisions. Their disagreements are becoming disruptive and slowing progress. The Developer often returns to earlier team decisions and re-opens the issue.
What are two ways to go about this problem?
(choose the best two answers)
A. At the Sprint Retrospective you observe whether the topic is raised. If it doesn’t happen, you check on how comfortable everybody is with the way team decisions are made.
B. To every team member expressing this concern you suggest raising this with the full team. You offer to help initiate the conversation but not to resolve the concern yourself.
C. You go to the Human Resources department and ask them to have a conversation with the Developer based on the issues the team has raised.
D. You take the Developer aside to express your concern over their disagreements and tell them to act as a team player and to comply with the team’s decision.
E. You organize an offsite team building activity in order to establish a foundation of trust. You observe whether the problem persists after the offsite activity.

Answering: “You are the Scrum Master of a Scrum Team that has one Developer who disagrees with team decisions. Their disagreements are becoming disruptive and slowing progress. The Developer often returns to earlier team decisions and re-opens the issue.” Read More »

Answering: “The Scrum Master is a Servant Leader. How does a Scrum Master demonstrate Servant Leadership?”

The Scrum Master is a Servant Leader. How does a Scrum Master demonstrate Servant Leadership?
(choose the best two answers)
A. The Scrum Master facilitates Scrum Events as requested or needed.
B. The Scrum Master coaches the Developers, the Product Owner and the organization how to work empirically.
C. The Scrum Master never intervenes in matters of the Developers, maximizing their autonomy and freedom.
D. The Scrum Master resolves every impediment that the Scrum Team runs into.

Answering: “The Scrum Master is a Servant Leader. How does a Scrum Master demonstrate Servant Leadership?” Read More »

Answering: “The items at the top of the Product Backlog should be analyzed, estimated, and ordered adequately to begin a Sprint. This is referred to as an actionable, or “Ready”, Product Backlog. At the start of the Sprint Planning, select the best description of the Product Backlog items that the Product Owner wants to have done.”

The items at the top of the Product Backlog should be analyzed, estimated, and ordered adequately to begin a Sprint. This is referred to as an actionable, or “Ready”, Product Backlog. At the start of the Sprint Planning, select the best description of the Product Backlog items that the Product Owner wants to have done.
(choose the best answer)
A. They are stated as User Stories and cannot be epics.
B. They are stated as User Stories or use cases and a plan to validate them has been established.
C. They are refined, and understood by the Product Owner and the Developers such that a forecast of items can be made to achieve the Sprint Goal.
D. They are fully described as User Stories or use cases already decomposed into tasks that will require no more than one person day to complete by the Developers.

Answering: “The items at the top of the Product Backlog should be analyzed, estimated, and ordered adequately to begin a Sprint. This is referred to as an actionable, or “Ready”, Product Backlog. At the start of the Sprint Planning, select the best description of the Product Backlog items that the Product Owner wants to have done.” Read More »

You cannot copy content of this page

$35 Exam Preps

Sale Ending Soon

Day
Hour
Min
Sec
Offer Expired
Add Your Heading Text Here