Answering: “In an environment where user acceptance testing is required before the Increment can be put into production, a development manager proposes to have user acceptance testing done every third Sprint because the feedback from the user acceptance tests is disrupting work in Sprints. Is this a good idea?”
In an environment where user acceptance testing is required before the Increment can be put into production, a development manager proposes to have user acceptance testing done every third Sprint because the feedback from the user acceptance tests is disrupting work in Sprints. Is this a good idea?
(choose the best answer)
A. No, the Increment will not be transparent and the feedback loops is too long.
B. It depends on what is stated in their Definition of Done.
C. Yes, the Scrum Team is a self-managing team.
D. Yes, the Scrum Team needs stability in the Sprint.