Answering: “What is the purpose of Nexus Sprint Retrospective?”

What is the purpose of Nexus Sprint Retrospective?
(choose the best answer)
A. Plan ways to increase quality and effectiveness across the whole Nexus.
B. To inspect how the last Sprint went with regards to individuals, teams, interactions, processes, tools, and its Definition of Done.
C. To complement the Scrum Teams’ Sprint Retrospectives by using bottom-up intelligence to focus on issues that affect the Nexus as a whole.
D. All of the above.

Answering: “What is the purpose of Nexus Sprint Retrospective?” Read More »

Answering: “From the list below, what is the most important concern for multiple Scrum Teams when they are working from the same Product Backlog?”

From the list below, what is the most important concern for multiple Scrum Teams when they are working from the same Product Backlog?
(choose the best answer)
A. Meeting original scope projections.
B. Clear definition of requirements.
C. Minimizing dependencies between teams.
D. Making sure there is enough work for everyone on every team.

Answering: “From the list below, what is the most important concern for multiple Scrum Teams when they are working from the same Product Backlog?” Read More »

Answering: “The Scrum Teams in a Nexus find they have simply too much work each Sprint to do to deliver a valuable and useful Increment. What could they try to improve their ability to produce an Increment in the next Sprint?”

The Scrum Teams in a Nexus find they have simply too much work each Sprint to do to deliver a valuable and useful Increment. What could they try to improve their ability to produce an Increment in the next Sprint?
(choose the best answer)
A. Reduce the amount of work that the teams pull into the Sprint.
B. Add another Scrum Team to the Nexus to increase capacity.
C. Reduce the number of Scrum Teams to reduce complexity.
D. Ask the Nexus Integration Team to extend the Sprint to allow more time for integration.

Answering: “The Scrum Teams in a Nexus find they have simply too much work each Sprint to do to deliver a valuable and useful Increment. What could they try to improve their ability to produce an Increment in the next Sprint?” Read More »

Answering: “There are five Scrum Teams working on a Product. During the Nexus Sprint Review, the teams present the results of the Sprint. After introductions, each team takes time to present their work for inspection by individually showing the new features they have built. They are not using a shared environment. The stakeholders do not provide much feedback. The event ends and people filter out of the room. Since teams are not using a shared environment, what is likely?”

[color=#6495ed]Scenario A: Nexus Sprint Review with Five Scrum Teams[/color]
There are five Scrum Teams working on a Product. During the Nexus Sprint Review, the teams present the results of the Sprint. After introductions, each team takes time to present their work for inspection by individually showing the new features they have built. They are not using a shared environment. The stakeholders do not provide much feedback. The event ends and people filter out of the room.
Since teams are not using a shared environment, what is likely?
(choose the best two answers)
A. The Nexus has not yet reached the integration phase.
B. The Sprint is too short.
C. The Nexus Integration Team is lacking or nonexistent.
D. There is no single Integrated Increment.

Answering: “There are five Scrum Teams working on a Product. During the Nexus Sprint Review, the teams present the results of the Sprint. After introductions, each team takes time to present their work for inspection by individually showing the new features they have built. They are not using a shared environment. The stakeholders do not provide much feedback. The event ends and people filter out of the room. Since teams are not using a shared environment, what is likely?” Read More »

Answering: “If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?”

If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?
(choose the best answer)
A. Its productivity is likely to decrease.
B. Its productivity is likely to increase.
C. Its productivity is likely to stay the same.

Answering: “If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?” Read More »