Answering: “When using Kanban, it is useful to have explicit policies. What existing elements in the Scrum Guide might be used as explicit policies?”

When using Kanban, it is useful to have explicit policies. What existing elements in the Scrum Guide might be used as explicit policies?
(choose the best answer)
A. Definition of Done.
B. Sprint Goal.
C. Product Backlog refinement.
D. All of the above.

Answering: “When using Kanban, it is useful to have explicit policies. What existing elements in the Scrum Guide might be used as explicit policies?” Read More »

Answering: “True or False: A Scrum Team using Kanban does not need to craft a Sprint Goal during Sprint Planning. Then can instead create one ‘on-demand’ as new work flows into the Sprint Backlog.”

True or False: A Scrum Team using Kanban does not need to craft a Sprint Goal during Sprint Planning. Then can instead create one ‘on-demand’ as new work flows into the Sprint Backlog.
A. True
B. False

Answering: “True or False: A Scrum Team using Kanban does not need to craft a Sprint Goal during Sprint Planning. Then can instead create one ‘on-demand’ as new work flows into the Sprint Backlog.” Read More »

Answering: “Which of the following metrics are likely to be reviewed during flow-based Daily Scrum?”

Which of the following metrics are likely to be reviewed during flow-based Daily Scrum?
(choose the best two answers)
A. Work Item Age.
B. Velocity.
C. Cycle Time.
D. Throughput.
E. Work in Progress (WIP).
F. Lead Time.
G. Process control chart and Scrum Team’s 85th percentile.

Answering: “Which of the following metrics are likely to be reviewed during flow-based Daily Scrum?” Read More »

Answering: “What does it mean when a Scrum Team chooses to communicate an 85% 5-day service level expectation (SLE)?”

What does it mean when a Scrum Team chooses to communicate an 85% 5-day service level expectation (SLE)?
(choose the best answer)
A. In the last Sprint the team has been able to complete 85% of Product Backlog items within 5 days of starting work on the item.
B. The team promises to have 85% of all Product Backlog items done within 5 days.
C. The team can get any critical system backup within 5 days.
D. The team expects they will complete a work item within 5 days of when they start working on it 85% of the time.

Answering: “What does it mean when a Scrum Team chooses to communicate an 85% 5-day service level expectation (SLE)?” Read More »