Answering: “While under development the environment in which a product will be used changed. What is the effect on the Product Backlog?”

While under development the environment in which a product will be used changed. What is the effect on the Product Backlog?
(choose the best answer)
A. It is archived and a new Product Backlog is created to take its place.
B. There is no effect, because it has to stay the same until the end of the project.
C. It evolves to reflect what the product needs to be most valuable.
D. It is converted into a requirements specification to ensure stability.

Answering: “While under development the environment in which a product will be used changed. What is the effect on the Product Backlog?” Read More »

Answering: “When do Scrum Team members take ownership of a Sprint Backlog item?”

When do Scrum Team members take ownership of a Sprint Backlog item?
(choose the best answer)
A. At the Sprint planning meeting.
B. Never. An individual item may be done by a single member, however, all Developers on the Scrum Team share ownership for items in the Sprint Backlog.
C. Whenever a team member can accommodate more work.
D. During the Daily Scrum.

Answering: “When do Scrum Team members take ownership of a Sprint Backlog item?” Read More »

Answering: “During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?”

During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?
(choose the best answer)
A. When the Product Owner identifies new work.
B. When the Scrum Master has time to enter it.
C. During the Daily Scrum after the Developers approve it.
D. As soon as possible after it is identified.

Answering: “During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?” Read More »

Answering: “The Developers should not be interrupted during the Sprint. The Sprint Goal should remain intact. These are conditions that foster creativity, quality and productivity. Based on this, which of the following is FALSE?”

The Developers should not be interrupted during the Sprint. The Sprint Goal should remain intact. These are conditions that foster creativity, quality and productivity. Based on this, which of the following is FALSE?
(choose the best answer)
A. The Product Owner can help clarify or optimize the Sprint when asked by the Developers.
B. The Developers may work with the Product Owner to remove or add work if they find they have more or less capacity than they expected.
C. As a decomposition of the selected Product Backlog Items, the Sprint Backlog changes and may grow as the work emerges.
D. The Sprint Backlog is fully formulated in Sprint Planning and does not change during the Sprint.

Answering: “The Developers should not be interrupted during the Sprint. The Sprint Goal should remain intact. These are conditions that foster creativity, quality and productivity. Based on this, which of the following is FALSE?” Read More »

You cannot copy content of this page

$35 Exam Preps

Sale Ending Soon

Day
Hour
Min
Sec
Offer Expired
Add Your Heading Text Here