A valuable, useful Increment must be available at the end of every Sprint. Scrum has no release Sprint, acceptance testing phase or wait for the Product Owner’s request.
Exam Question
For the purpose of transparency, when does Scrum say a valuable and useful Increment must be available? (choose the best answer)
- A. Before the Release Sprint.
- B. After the Acceptance Testing phase.
- C. At the end of every Sprint.
- D. Every 3 Sprints.
- E. When the Product Owner asks to create one.
Correct Answer
C. At the end of every Sprint.
Why This Is the Correct Answer
The Scrum Guide describes Sprints as “the heartbeat of Scrum, where ideas are turned into value.” Each Sprint must produce at least one Increment that meets the Definition of Done, because the Increment is what makes progress transparent. At the Sprint Review, the Scrum Team and stakeholders inspect it and decide what to do next. If usable work only appeared every few Sprints or after a separate phase, the team would be inspecting plans and partial work instead of reality. The Product Owner may decide not to release a given Increment, but it must still be done and usable.
Why the Other Options Are Wrong
A. Before the Release Sprint. Scrum does not include Release Sprints. Their existence suggests a weak Definition of Done.
B. After the Acceptance Testing phase. Testing happens within every Sprint as part of the Definition of Done, not in a separate phase.
D. Every 3 Sprints. Spacing out Increments reduces transparency and delays feedback.
E. When the Product Owner asks for one. Releasing is the Product Owner’s call, but having a usable Increment is required every Sprint regardless.
Exam Tip
Separate two ideas: creating a Done Increment is required every Sprint, while releasing it is a business decision. Questions often blur them.
Key Takeaways
- Every Sprint ends with a usable Increment.
- The Increment makes progress transparent.
- Releasing is optional; being Done is not.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- True or False: An Increment must be released to customers or users at the end of each Sprint.” (PSM I)
- When many Scrum Teams are working on the same product, should all of their Increments be integrated every Sprint?” (PSM I)
- When must a Scrum Team release each Increment?” (PSM I)
- Which of these may a Scrum Team deliver at the end of a Sprint?” (PSM I)
- Which of the following best describes an increment of working software?