Answering: “Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started using the product. The stakeholder is unhappy with the slow performance, a complaint that the Product Owner agrees on. How will you move this forward?”
Several Sprints into a project, the Product Owner tells the Scrum Master that a key stakeholder just started using the product. The stakeholder is unhappy with the slow performance, a complaint that the Product Owner agrees on. How will you move this forward?
(choose the best answer)
A. Wait to bring this up in the next Sprint Retrospective as this is the appropriate
time for the Scrum Team to re-consider the Definition of Done.
B. Bring the concern to the testers in the Scrum Team and ask them to improve how the system is tested.
C. Explain to the Product Owner that it’s up to the Developers to decide on acceptable performance standards as they own the Definition of Done.
D. Encourage the Product Owner to bring the performance concerns to the Developers and work with them on how to improve performance, and ultimately have stronger Definition of Done.