Answering: “True or False: Sprint Reviews are an opportunity to collect stakeholder feedback.”
True or False: Sprint Reviews are an opportunity to collect stakeholder feedback.
A. True
B. False
True or False: Sprint Reviews are an opportunity to collect stakeholder feedback.
A. True
B. False
True or False: The Product Owner should have the entire Product Backlog documented in detail before the first Sprint can start?
A. True
B. False
Which two things should the Scrum Team do during the first Sprint?
(choose the best two answers)
A. Create an Increment of potentially releasable software.
B. Analyze, describe, and document the requirements for the subsequent Sprints.
C. Develop at least one piece of functionality.
D. Make up a plan for the rest of the project.
E. Define the major product features and a release plan architecture.
Answering: “Which two things should the Scrum Team do during the first Sprint?” Read More »
When does a Developer become accountable for an item in the Sprint Backlog?
(choose the best answer)
A. At the Sprint Planning when all of the Sprint Backlog items are split evenly across the Developers.
B. Never. All Developers on the Scrum Team share accountability for items in the Sprint Backlog.
C. As soon as a Developer on the Scrum Team can accommodate more work.
D. During the Daily Scrum.
Answering: “When does a Developer become accountable for an item in the Sprint Backlog?” Read More »
When is the Sprint Backlog created?
(choose the best answer)
A. Prior to Sprint Planning.
B. During the Sprint Retrospective.
C. During refinement.
D. During Sprint Planning.
Answering: “When is the Sprint Backlog created?” Read More »
Which two things are appropriate for a Scrum Master to do, if the Scrum Team does not have the tools and environment to completely finish each selected Product Backlog item?
(choose the best two answers)
A. Refocus the current Sprint on establishing the Scrum Team’s environment instead of delivering an Increment.
B. Have the Scrum Team establish a Definition of Done that is actually possible to achieve given the current circumstances.
C. Declare the Scrum Team not ready for Scrum.
D. Encourage the Product Owner to accept partially done Increments until the situation improves.
E. Coach the Scrum Team to improve its skills, tools and environment over time and adjust the Definition of Done accordingly.
You cannot copy content of this page