Exam Question
Which two things are appropriate for a Scrum Master to do, if the Scrum Team does not have the tools and environment to completely finish each selected Product Backlog item?
(choose the best two answers)
A. Refocus the current Sprint on establishing the Scrum Team’s environment instead of delivering an Increment.
B. Have the Scrum Team establish a Definition of Done that is actually possible to achieve given the current circumstances.
C. Declare the Scrum Team not ready for Scrum.
D. Encourage the Product Owner to accept partially done Increments until the situation improves.
E. Coach the Scrum Team to improve its skills, tools and environment over time and adjust the Definition of Done accordingly.
Correct Answer
B and E.
Why This Is the Correct Answer
An Increment exists only when work meets the Definition of Done. If the team sets a standard it has no means to reach, it will either fail every Sprint or quietly pretend to be done. Both destroy transparency. Starting with an achievable Definition of Done keeps every Increment honest, and the gap between that and a fully releasable product becomes visible for the Product Owner to manage. From there the Scrum Master coaches the team and works with the organization to get better tools, skills and environments. Each improvement lets the team strengthen its Definition of Done, which is how Scrum Teams grow their quality bar over time.
Why the Other Options Are Wrong
A. Spend the Sprint building the environment instead of an Increment. Scrum expects an Increment every Sprint. Improvements to the environment can be part of the Sprint’s work, but they do not replace delivering value.
C. Declare the team not ready for Scrum. Scrum is how the team will discover and remove these constraints. Waiting for perfect conditions means never starting.
D. Ask the Product Owner to accept partially done Increments. Undone work is not an Increment. Accepting it hides technical risk and misleads stakeholders.
Exam Tip
On the PSPO exam this scenario looks the same as on PSM I. Favor answers that protect transparency now and improve capability later.
Key Takeaways
- Set a Definition of Done the team can actually meet.
- Improve tools, skills and environment over time.
- Raise the Definition of Done as capability grows.

Get ready for the official PSPO I exam
320 PSPO I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.
More PSPO I exam questions
- The length of a Sprint should be:” (PSPO I)
- When might a Sprint be cancelled?” (PSPO I)
- What does it mean to say that an event has a timebox?” (PSPO I)
- When is a Product Backlog item considered complete?” (PSPO I)
- You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario.” (PSPO I)