A Product Backlog item is complete when it meets the Definition of Done. Passing acceptance criteria or reaching the end of the Sprint is not enough on its own.
Exam Question
When is a Product Backlog item considered complete?
(choose the best answer)
A. At the end of the Sprint.
B. When the item passes all acceptance criteria.
C. When the item meets the Definition of Done.
D. When the item has gained product sponsor approval.
Correct Answer
C. When the item meets the Definition of Done.
Why This Is the Correct Answer
The Scrum Guide states “The moment a Product Backlog item meets the Definition of Done, an Increment is born.” It also says that work cannot be considered part of an Increment unless it meets the Definition of Done. Acceptance criteria, if a team uses them, describe what a specific item should do. The Definition of Done describes the quality standard that applies to every item, such as testing, integration and security checks. An item can satisfy its own acceptance criteria and still fail that broader standard, so the Definition of Done is the deciding test.
Why the Other Options Are Wrong
A. At the end of the Sprint. Time passing does not make work Done. Items can be completed during the Sprint or not at all.
B. When it passes all acceptance criteria. Acceptance criteria are item-specific and optional. They do not replace the shared quality standard of the Definition of Done.
D. When a product sponsor approves it. Scrum has no sponsor sign-off step. The Definition of Done is the objective test of completion.
Exam Tip
If a question asks when work is complete or Done, the answer is the Definition of Done. Approvals and acceptance criteria are common distractors.
Key Takeaways
- Done means meeting the Definition of Done.
- An Increment is born the moment an item is Done.
- Acceptance criteria complement, but do not replace, the Definition of Done.

Get ready for the official PSPO I exam
320 PSPO I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.
More PSPO I exam questions
- You have just been hired by a company new to Scrum. Your management has assigned you to be the Scrum Master of six new Scrum Teams. These teams will build one product. Select two conditions you should strive for in this scenario.” (PSPO I)
- Who is accountable for clearly expressing Product Backlog items
- Who starts the Daily Scrum
- An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done?” (PSPO I)
- A Scrum Master is working with a Scrum Team that has Developers in different physical locations. The Developers meet in a variety of meeting rooms and have much to do logistically (for example: reserve meetings rooms and set up conference calls) before the Daily Scrum. What action should the Scrum Master take?” (PSPO I)