Answering: “Your Scrum Team’s cycle time is currently 8 days or less with 85% confidence. The team has set the Service Level Expectations (SLE) accordingly. If an item in progress has just aged past your dataset’s 50th percentile, what can we say about the chance it will fail to meet the team’s 8-day SLE?”
Your Scrum Team’s cycle time is currently 8 days or less with 85% confidence. The team has set the Service Level Expectations (SLE) accordingly. If an item in progress has just aged past your dataset’s 50th percentile, what can we say about the chance it will fail to meet the team’s 8-day SLE?
(choose the best answer)
A. There is now a higher chance to meet the team’s SLE.
B. There is now a lower chance it will meet the team’s SLE.
C. We cannot predict with any level of confidence what will happen with the work item at this point.
D. Nothing changed. We’re still 85% confident the card will meet the SLE.