Answering: “Developers are blocked by an impediment in the middle of the Sprint. The impediment is outside the Developer’s control. What should they do?”
Developers are blocked by an impediment in the middle of the Sprint. The impediment is outside the Developer’s control. What should they do?
(choose the best answer)
A. Cancel the Sprint.
B. Immediately raise the issue to the Scrum Master.
C. Complete the work that can be done and complete the remainder during the “hardening sprint”.
D. Stop using Scrum.
E. Drop the Product Backlog items affected by the impediment from the Sprint Plan.