Refining Product Backlog items is a crucial activity in Scrum that ensures the team has a clear understanding of the work required and can plan effectively for upcoming Sprints. During refinement, the Scrum Team collaborates to break down, analyze, and estimate the work required to deliver the Product Backlog items.
Exam Question
What three things happen when refining Product Backlog items?
(choose the best three answers)
A. Programming.
B. Product Backlog item decomposition.
C. Analysis.
D. Feature Testing.
E. Sizing.
Correct Answers
B. Product Backlog item decomposition.
C. Analysis.
E. Sizing.
Explanation
Correct Answers
B. Product Backlog item decomposition:
Decomposition involves breaking down larger Product Backlog items into smaller, more manageable pieces. This helps the team understand the scope of work and ensures that each item can be completed within a Sprint. Decomposition makes it easier to plan and execute the work during the Sprint.
C. Analysis:
Analysis is an essential part of refining Product Backlog items. During analysis, the Scrum Team evaluates the details of the Product Backlog items to understand what is required to complete them. This process may involve discussing dependencies, potential risks, and the technical approach to be taken.
E. Sizing:
Sizing, often done using estimation techniques like story points, involves determining the effort required to complete a Product Backlog item. Sizing helps the team gauge the complexity and amount of work involved, which is critical for effective Sprint planning.
Why the Other Options Are Less Appropriate
A. Programming:
Programming is not typically part of the refinement process. Refinement focuses on preparing the Product Backlog items for future Sprints by understanding and estimating the work, not on writing code. Programming occurs during the Sprint when the Developers work on the selected Product Backlog items.
D. Feature Testing:
Feature testing is part of the development process that happens during the Sprint, not during refinement. While the Scrum Team might discuss testing strategies during refinement, the actual testing of features occurs after the code has been developed.
Relevance to the PSD Exam
Understanding the activities involved in refining Product Backlog items is crucial for the PSD exam. It demonstrates knowledge of how to prepare work for upcoming Sprints, ensuring that the team can effectively plan and execute their tasks.
Key Takeaways
- Product Backlog Refinement: Involves decomposition, analysis, and sizing of Product Backlog items to prepare them for future Sprints.
- Effective Planning: Refinement ensures that the Scrum Team has a clear understanding of the work required and can plan their Sprints effectively.
- Collaboration: The entire Scrum Team collaborates during refinement to ensure that everyone understands the work and can contribute to the planning process.
Conclusion
Refining Product Backlog items is a vital process that ensures the Scrum Team is well-prepared for upcoming Sprints. By decomposing, analyzing, and sizing the items, the team can effectively plan their work and deliver valuable Increments.

Get ready for the official PSD exam
127 PSD practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSD exam fee ($200) is paid separately to Scrum.org.
More PSD exam questions
- You are asked to refactor part of the codebase for Application X. When you are done, all unit tests pass with 50% code coverage. What can you infer from this?
- What is the practice of branching code in a version control system?
- When can Product Backlog refinement occur?
- Which of the following is an example of an Increment?” (PSD)
- True or False: Developers do not meet with stakeholders; only the Product Owner meets with stakeholders.” (PSD)