The Scrum Team as a whole is responsible for collaborating with stakeholders. It is not handed off to a manager, an analyst or just the Developers.
Exam Question
Who is responsible for collaboration with stakeholders?
(choose the best answer)
A. The Team Manager.
B. The Business Analyst.
C. The Project Manager.
D. The Developers.
E. The Scrum Team.
Correct Answer
E. The Scrum Team.
Why This Is the Correct Answer
The Scrum Guide says “the Scrum Team is responsible for all product-related activities from stakeholder collaboration, verification, maintenance, operation, experimentation, research and development, and anything else that might be required.” Stakeholder collaboration is listed first. The Product Owner often leads it by representing stakeholder needs in the Product Backlog, but the Developers and Scrum Master also work with stakeholders, for example at the Sprint Review. Keeping this within the Scrum Team avoids relays through intermediaries, which slow feedback and distort what users need.
Why the Other Options Are Wrong
A. The Team Manager. Scrum has no team manager. Placing collaboration outside the team breaks direct feedback.
B. The Business Analyst. Business analyst is not a Scrum accountability. Any analysis work belongs to the Scrum Team.
C. The Project Manager. Scrum has no project manager role. The Scrum Team handles product-related activities itself.
D. The Developers. Developers do collaborate with stakeholders, but responsibility belongs to the whole Scrum Team, including the Product Owner and Scrum Master.
Exam Tip
When the answer choices include “Scrum Team” and the activity is product-related, check whether the Scrum Guide gives it to the whole team. Stakeholder collaboration is one such case.
Key Takeaways
- Stakeholder collaboration belongs to the whole Scrum Team.
- The Product Owner often leads but does not own it alone.
- Intermediaries outside the team slow down feedback.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee is paid separately to Scrum.org.
More PSM I exam questions
- Which statement best describes a Product Owner’s responsibility?” (PSM I)
- What is Product Owner work that a Product Owner might delegate?
- Which is the most important stakeholder Product Owners must satisfy?
- How often should customer satisfaction be measured?” (PSM I)
- Why is it important that there is only one Product Owner per product?” (PSM I)