When several Scrum Teams work on one product, they must mutually define and comply with the same Definition of Done. Separate definitions, later reconciliation or a definition set by Scrum Masters do not produce one integrated Increment.
Exam Question
When multiple Scrum Teams are working on a single product, what best describes the Definition of Done?
(choose the best answer)
A. Each Scrum Team uses its own, but must make their definition clear to all other Teams so the differences are known.
B. Each Scrum Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.
C. The Scrum Masters from each Scrum Team define a common Definition of Done.
D. When multiple Scrum Teams are working together on a product, they must mutually define and comply with the same Definition of Done.
Correct Answer
D. When multiple Scrum Teams are working together on a product, they must mutually define and comply with the same Definition of Done.
Why This Is the Correct Answer
The Scrum Guide states: “If there are multiple Scrum Teams working together on a product, they must mutually define and comply with the same Definition of Done.” All teams contribute to one Increment, and it can only be releasable if every part meets the same standard. Teams can add stricter criteria of their own, but they cannot go below the shared definition. Defining it together gives every team ownership and a shared understanding of what done means for the product.
Why the Other Options Are Wrong
A. Each team uses its own and shares it with the others. Making differences visible does not fix them. The combined Increment would have inconsistent quality.
B. Each team uses its own and reconciles differences in a hardening Sprint. Hardening Sprints mean earlier work was not done. Scrum has no such Sprint.
C. The Scrum Masters define a common Definition of Done. The Scrum Teams define it together. The Scrum Masters may facilitate, but they do not own it.
Exam Tip
For multi-team questions about done, the answer almost always uses the Scrum Guide phrase “mutually define and comply with the same Definition of Done.”
Key Takeaways
- Teams on one product share one Definition of Done.
- They define it together and all comply with it.
- Hardening Sprints are a sign that work was not really done.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- A Project Manager working with your Scrum Team has raised concerns about progress and money spent. What are the two best responses?” (PSM I)
- The three pillars of empirical process control are:
- If burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate?” (PSM I)
- Sprint burndown charts are an efficient tracking tool, because they show:
- What are two effective ways for a Scrum Team to ensure security concerns are satisfied?