Exam Question
When is the Sprint Backlog created? (choose the best answer)
- A. Prior to Sprint Planning.
- B. During the Sprint Retrospective.
- C. During refinement.
- D. During Sprint Planning.
Correct Answer
D. During Sprint Planning.
Explanation
Why D is Correct
The Sprint Backlog is created during Sprint Planning. This event involves the entire Scrum Team and is dedicated to defining what can be delivered in the Sprint and how that work will be achieved. The Sprint Backlog includes the Sprint Goal, selected Product Backlog items, and a plan for delivering them.
Key Points
- Sprint Planning: The event where the Sprint Backlog is created.
- Collaboration: The entire Scrum Team collaborates to select items and create a plan.
- Guidance: The Sprint Backlog provides clear guidance on what the team aims to achieve during the Sprint.
Roles and Responsibilities in Scrum
- Developers: Work with the Product Owner to select items and create the Sprint Backlog.
- Scrum Master: Facilitates Sprint Planning, ensuring that the team creates a viable Sprint Backlog.
- Product Owner: Prioritizes and selects the most valuable items for the Sprint Backlog during Sprint Planning.
Relevance to the PSM I Exam
Understanding when the Sprint Backlog is created highlights the importance of Sprint Planning in the Scrum framework. This knowledge is crucial for the PSM I exam and for effectively implementing Scrum practices.
Conclusion
The Sprint Backlog is created during Sprint Planning, involving the entire Scrum Team in selecting and planning the work for the Sprint. This process ensures that the team has a clear and achievable plan for the Sprint.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- What should the Scrum Team do during the first Sprint?” (PSM I)
- True or False: The purpose of a Sprint is to produce a valuable, useful Increment.” (PSM I)
- What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the start of the next Sprint?” (PSM I)
- What three factors are best considered when establishing the Sprint length?
- True or False: Multiple Scrum Teams working on the same project must have the same Sprint start date.” (PSM I)