A clear Product Goal gives Sprints a shared direction, makes progress easier to inspect at the Sprint Review, and lets the team weigh decisions against it. It does not let anyone predict when the Product Backlog will be finished.

Exam Question

What are three advantages of a Product Owner sharing a clearly defined Product Goal with the Scrum Team?
(choose the best three answers)

  • A. It provides a good overall direction so Sprints will feel less like isolated pieces of work.
  • B. It is easier to inspect incremental progress at the Sprint Review.
  • C. It is not mandatory in Scrum. There is no real advantage.
  • D. It helps the Scrum Team keep focus and they can weigh any decision against the Product Goal.
  • E. It helps the Developers estimate the date that the Product Backlog will be complete.

Correct Answer

A, B and D.

Why This Is the Correct Answer

The Scrum Guide describes the Product Goal as “the long-term objective for the Scrum Team” and says it “describes a future state of the product which can serve as a target for the Scrum Team to plan against.” Each Sprint Goal is a step toward it, so Sprints connect to a bigger purpose. At the Sprint Review, the team and stakeholders can judge progress toward that future state. During the Sprint, any choice can be tested with one question: does this move us toward the Product Goal?

Why the Other Options Are Wrong

C. It is not mandatory in Scrum, so there is no real advantage. The Product Goal is a commitment in the 2020 Scrum Guide, attached to the Product Backlog. It is mandatory and very useful.

E. It helps the Developers estimate when the Product Backlog will be complete. The Product Backlog is emergent and never really complete. A goal gives direction, not a completion date.

Exam Tip

Remember the three commitments: Product Goal for the Product Backlog, Sprint Goal for the Sprint Backlog, Definition of Done for the Increment. Answers that call any of them optional are wrong.

Key Takeaways

  • The Product Goal is the Product Backlog’s commitment and is required.
  • It connects Sprint Goals into a long-term direction.
  • It helps inspection and decision-making, not date prediction.
Professional Product Owner PSPO I™ Exam Prep

Get ready for the official PSPO I exam

320 PSPO I practice questions, each with an in-depth explanation like the one above.

  • Practice Mode: study at your own pace and choose the test length.
  • Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.

$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.

More PSPO I exam questions

Practice all 320 PSPO I questions →