Pull System in the Scrum Framework
The concept of a pull system is integral to managing workflow efficiently by ensuring that work is initiated only when there is capacity to handle it.
Exam Question
True or False: The Scrum framework already contains elements that create a pull system.
A. True
B. False
Correct Answer
A. True
Explanation
Correct Answer
A. True:
The Scrum framework indeed contains elements that create a pull system. In Scrum, work is pulled into a Sprint during the Sprint Planning meeting. The team reviews the Product Backlog and selects the items they have the capacity to complete in the upcoming Sprint. This practice of selecting work based on capacity is a fundamental characteristic of a pull system.
Elements of Pull System in Scrum
- Sprint Planning: During Sprint Planning, the team pulls Product Backlog items into the Sprint Backlog based on their capacity and the Sprint Goal. This ensures that the team is not overloaded and can focus on completing the selected items.
- Daily Scrum: The Daily Scrum allows the team to reassess and manage the flow of work daily. If any impediments are identified, they can adjust their work accordingly, pulling in new tasks only when they have the capacity to do so.
- Work in Progress (WIP) Limits: While not explicitly mentioned in Scrum, teams often implement WIP limits as part of their process to manage flow and ensure that they are not starting new work until current work is completed.
Importance of Pull Systems
- Flow Management: Pull systems help manage the flow of work, ensuring that the team is not overwhelmed and can maintain a steady pace.
- Efficiency: By only starting new work when there is capacity, teams can reduce multitasking and improve efficiency.
- Focus: Pull systems help teams focus on completing current work before taking on new tasks, leading to higher quality and more predictable outcomes.
Relevance to the PSK I Exam
Understanding how the Scrum framework incorporates elements of a pull system is crucial for the PSK I exam. It demonstrates knowledge of how Scrum naturally integrates principles that enhance workflow management and efficiency.
Key Takeaways
- The Scrum framework includes elements that create a pull system, such as Sprint Planning and Daily Scrums.
- These elements help manage the flow of work, ensuring that the team is not overloaded and can focus on completing tasks efficiently.
- Implementing WIP limits can further enhance the pull system within the Scrum framework.
Conclusion
The Scrum framework inherently includes elements that create a pull system, ensuring efficient workflow management and focus on task completion.

Get ready for the official PSK I exam
115 PSK I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 45 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSK I exam fee ($200) is paid separately to Scrum.org.
More PSK I exam questions
- What is the potential benefit of limiting Work in Progress (WIP)?
- True or False: When the Developers add Kanban to Scrum, the way they use the Sprint Goal during their Daily Scrum changes.
- When using Kanban in a Scrum environment, some resistance may be found to introducing Work in Progress (WIP) Limits. What is an alternative to introducing WIP Limits in Kanban?
- True or False: Work Item Age is a leading indicator for the length of the Scrum Team’s feedback loop for that (in progress) item.
- What might be considered during the Sprint Retrospective once a team decides to supplement their Scrum with Kanban?