A Product Owner’s job centers on working with customers and stakeholders to find the most valuable work, and on keeping them informed about where the product is heading. Writing user stories and being on call all day are not the core of the role.
Exam Question
The job of a Product Owner focuses on the following:
(choose the best two answers)
A. Writing clear, transparent User Stories.
B. Working with customers and stakeholders to identify the most valuable product requirements.
C. Being with the Scrum Team all the time, just in case they need me to clarify a requirement.
D. Clearly communicating project or release status and strategies to customers and stakeholders.
Correct Answer
B and D.
Why This Is the Correct Answer
The Product Owner is “accountable for maximizing the value of the product resulting from the work of the Scrum Team.” That value comes from understanding customers and stakeholders well enough to decide what matters most, and from making those decisions and the strategy behind them transparent. Clear communication of release plans and status keeps stakeholders’ expectations realistic and builds trust in the Product Owner’s choices.
Why the Other Options Are Wrong
A. Writing clear, transparent User Stories. User stories are one optional format for Product Backlog items. The Product Owner is accountable for clear items, but anyone, including the Developers, can write them, and Scrum does not require stories at all.
C. Being with the Scrum Team all the time in case a requirement needs clarifying. The Product Owner should be available, but a role spent waiting next to the team leaves no time for the stakeholder work that actually drives value.
Exam Tip
The PSPO I exam favors answers about value, stakeholders and strategy over answers about documentation formats or constant presence.
Key Takeaways
- The Product Owner maximizes value by understanding customers and stakeholders.
- Transparent communication of plans and progress is part of the job.
- User stories are optional and do not define the role.

Get ready for the official PSPO I exam
320 PSPO I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.
More PSPO I exam questions
- A Scrum Team is a cohesive unit of professionals that consists of which of the following?” (PSPO I)
- When does a Developer become accountable for the value of a Product Backlog item selected for the Sprint?
- A Product Owner is accountable for maximizing the value of the product that is the result of the work of the Scrum Team. Which of the following can be delegated to others, while the Product Owner remains accountable for the work?
- The Definition of Done serves which three purposes?” (PSPO I)
- Which statement best describes the Sprint Backlog as the output of the Sprint Planning?” (PSPO I)