Scrum Team membership can change as needed, but the team should expect a short-term drop in productivity when it does. Changes are allowed, and their cost should be considered.
Exam Question
How often should Scrum Team membership change? (choose the best answer)
- A. Every Sprint to promote shared learning.
- B. As needed, while taking into account a short-term reduction in productivity.
- C. Never, because it reduces productivity.
- D. As needed, with no special allowance for changes in productivity.
Correct Answer
B. As needed, while taking into account a short-term reduction in productivity.
Why This Is the Correct Answer
Scrum does not lock team membership, and the Scrum Guide says teams may reorganize into multiple cohesive Scrum Teams when they grow too large. Every change still disrupts how the team works together. New members need to learn the product, the codebase and the team’s habits, and the existing members need to adjust. Teams usually go through a period of lower productivity while they settle. Changing membership when there is a real need, such as missing skills or a new product focus, is fine. Making changes without accounting for the dip leads to false expectations.
Why the Other Options Are Wrong
A. Every Sprint to promote shared learning. Constant rotation keeps the team from ever building stable working relationships. The learning gained does not offset the loss.
C. Never, because it reduces productivity. Teams sometimes need new skills or a new shape. A rule of never would stop useful changes.
D. As needed, with no allowance for productivity changes. This ignores a real effect. Plans and forecasts should reflect the dip after a team change.
Exam Tip
Look for the balanced option. Scrum.org answers rarely say “never” or “every Sprint” about team changes, and favor change with eyes open to its cost.
Key Takeaways
- Team membership may change when there is a real need.
- Every change causes a short-term productivity dip.
- Stable teams are preferred but not mandatory.

Get ready for the official PSM I exam
480 PSM I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.
More PSM I exam questions
- What are two responsibilities of testers in a Scrum Team?
- Which of the following are the Developers accountable for?
- In accordance with Scrum theory, how should a group of 100 people be divided into multiple Scrum Teams?” (PSM I)
- What is the typical size for a Scrum Team?” (PSM I)
- During a Sprint, it has been determined that the Developers will not be able to finish the complete forecast. Who should be present to review and adjust the Sprint work selected?