PSM I exam question

Answering: “What are two responsibilities of testers in a Scrum Team?”

By Hiro TakashimyaUpdated
Studying for the PSM I exam? Try 20 free practice questions first.Start the free quiz →

Responsibilities of Testers in a Scrum Team

In Scrum, there is no separate role for testers; instead, the responsibility of ensuring quality is shared among the Developers. This approach promotes collaboration and collective ownership of the product quality.

Exam Question

What are two responsibilities of testers in a Scrum Team? (choose the best two answers)

  • A. Scrum has no “tester” role.
  • B. Finding bugs.
  • C. Verifying the work of programmers.
  • D. Tracking quality metrics.
  • E. The Developers are responsible for quality.

Correct Answers

A. Scrum has no “tester” role.
E. The Developers are responsible for quality.

Explanation

Why A and E are Correct

A. Scrum has no “tester” role: In Scrum, there are no predefined roles such as testers or quality assurance engineers. Instead, the Scrum framework promotes a cross-functional team where Developers take on various responsibilities, including testing and ensuring the quality of the product.

E. The Developers are responsible for quality: The Developers in a Scrum Team are collectively responsible for the quality of the product. This means they must ensure that all work meets the Definition of Done, which includes rigorous testing and validation.

Why B, C, and D are Incorrect

B. Finding bugs: While finding bugs is part of ensuring quality, in Scrum, this responsibility is not assigned to a separate tester role but is a collective responsibility of the Developers.

C. Verifying the work of programmers: Verification of work is part of the collaborative effort among Developers, rather than being a distinct responsibility of a separate tester role.

D. Tracking quality metrics: Although tracking quality metrics is important, it is not a specific responsibility assigned to testers in Scrum. The Scrum Team as a whole focuses on delivering quality through continuous improvement and adherence to the Definition of Done.

Key Points

  • Cross-Functional Team: In Scrum, all Developers share the responsibility for quality, including testing and verification.
  • Collective Ownership: Ensuring quality is a collective effort, with no separate tester role.

Responsibilities in Scrum

  • Product Owner: Ensures the Product Backlog is ordered and refined to maximize value and align with the team’s capacity.
  • Scrum Master: Facilitates Scrum events, removes impediments, and helps teams adhere to Scrum principles.
  • Developers: Collaborate to complete all tasks necessary to deliver a potentially shippable Increment, ensuring all work meets the Definition of Done, including testing and quality assurance.

Relevance to the PSM I Exam

Understanding the responsibilities of the Scrum Team, particularly the collective ownership of quality, is crucial for the PSM I exam. This knowledge highlights the importance of cross-functional teams and the absence of traditional roles such as testers in Scrum.

Conclusion

In Scrum, there is no separate tester role. Instead, the Developers are collectively responsible for ensuring the quality of the product. This approach promotes collaboration, shared responsibility, and continuous improvement within the Scrum Team.

Scrum Master PSM I™ Exam Prep

Get ready for the official PSM I exam

480 PSM I practice questions, each with an in-depth explanation like the one above.

  • Practice Mode: study at your own pace and choose the test length.
  • Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.

$29 is ScrumPrep's one-time price. The official PSM I exam fee ($200) is paid separately to Scrum.org.