The Sprint Goal is created during Sprint Planning by the whole Scrum Team. It is not set before planning, not optional, and not written at random points in the Sprint.
Exam Question
When should a Sprint Goal be created?
(choose the best answer)
A. During Sprint Planning.
B. It should have been created in the previous Sprint during Product Backlog refinement.
C. A Sprint Goal is not mandatory in Scrum.
D. At any time during the Sprint.
E. It must be established before Sprint Planning in order to begin planning.
Correct Answer
A. During Sprint Planning.
Why This Is the Correct Answer
The first topic of Sprint Planning is why the Sprint is valuable. The Scrum Guide says the Product Owner proposes how the product could increase its value and utility, and “The whole Scrum Team then collaborates to define a Sprint Goal that communicates why the Sprint is valuable to stakeholders.” The Guide adds that “The Sprint Goal must be finalized prior to the end of Sprint Planning.” The Product Owner may arrive with an idea or proposed objective, and refinement in the previous Sprint helps prepare. The goal itself is created and agreed on in this event.
Why the Other Options Are Wrong
B. In the previous Sprint during refinement. Refinement prepares Product Backlog items. The Sprint Goal is created by the Scrum Team at Sprint Planning.
C. A Sprint Goal is not mandatory. Every Sprint has a Sprint Goal. It is the commitment for the Sprint Backlog.
D. At any time during the Sprint. The Sprint Goal must be finalized before Sprint Planning ends, so it can guide the whole Sprint.
E. Before Sprint Planning. The Product Owner may bring a proposal, but the Sprint Goal is defined collaboratively in Sprint Planning.
Exam Tip
Remember the distinction between a Product Owner’s proposal and the Sprint Goal. The proposal may come earlier; the goal is defined and finalized in Sprint Planning.
Key Takeaways
- The Scrum Team creates the Sprint Goal in Sprint Planning.
- It must be finalized before planning ends.
- Every Sprint has a Sprint Goal.

Get ready for the official PSPO I exam
320 PSPO I practice questions, each with an in-depth explanation like the one above.
- Practice Mode: study at your own pace and choose the test length.
- Mock Exam Mode: 80 random questions in 60 minutes, like the real exam.
$29 is ScrumPrep's one-time price. The official PSPO I exam fee ($200) is paid separately to Scrum.org.
More PSPO I exam questions
- A new Developer is having continuing conflicts with existing members of the Scrum Team, which is impacting the delivery of the Increment. If necessary, who is responsible for removing the Developer from the Scrum Team?
- User documentation is part of your Definition of Done. However, there are not enough technical writers for all teams. Your Scrum Team does not have a Technical Writer. What should the Scrum Team do?” (PSPO I)
- A Project Manager working with your Scrum Team has raised concerns about progress and money spent. What are the two best responses?” (PSPO I)
- True or False: The Product Owner should have the entire Product Backlog documented in detail before the first Sprint can start?” (PSPO I)
- Which two things should the Scrum Team do during the first Sprint?