1A project manager has reviewed the lessons learned from past projects as well as the project charter to gain a high-level understanding of project goals and constraints. Which data gathering technique is best for the project manager to use to develop the project management plan? (choose the best answer)
2Due to the worldwide outbreak of a new deadly virus, the World Health Organization (WHO) issues a bid for pharmaceutical companies to develop a vaccine against the virus. The goal is clear – preventing the virus from spreading. The solution, though, is far from being defined. However, once the vaccine is developed, the approval process is very formal and structured. What project management approach is best for this project? (choose the best answer)
3A vendor did not perform as contracted, so you are withholding payment as stipulated by the contract. The vendor started using foul language and is calling you names. Your team members are furious, and some of them have responded similarly. Even though you are angry as well, you stay calm and handle the situation with respect. Which of the following have you demonstrated by responding to the situation in this way? (choose the best answer)
4A team of generalizing specialists with expertise in adaptive organizational change is assigned to a project that will change the organizational structure from a weak matrix to a project-oriented organizational type. The product owner is concerned that the broad impact of the change will cause significant resistance by those affected by the change. What is the best strategy for the project team to assist with change adoption? (choose the best answer)
5As the project team demonstrates the product increment developed during the last sprint, an influential business stakeholder throws offensive comments about the product. When the product owner asks for details, the stakeholder does not cooperate. As the meeting goes on, the team realizes that the stakeholder has negative perceptions about the project. What should the team do? (choose the best answer)
6A Product Owner meets with the agile team and stakeholders to prioritize features in the Product Backlog. Each feature is categorized based on the risk associated with its development and the value the feature provides to the customer. Which features should the Product Owner prioritize to be developed first in order to maximize the probability of project success? (choose the best answer)
7As part of a periodic risk review, the steering committee members express concern about a significant risk that the project team missed identifying while planning the previous sprint. At the following sprint planning meeting, the project manager and team devise an appropriate, cost-effective, and realistic response plan and assign a risk owner. What else should the project manager do? (choose the best answer)
8A project manager is wrapping up the hardware development phase of a project. The project will now transition to the software development phase. Unlike the hardware development phase, where requirements were clearly defined, the software development phase is characterized by unclear requirements that are going to change often as the phase progresses. How might the project manager's role, as an integrator, change with this transition? (choose the best answer)
9A software development project is in planning. After applying all available schedule compression techniques to the max, the project manager squeezes the schedule into 18 months duration and submits the project management plan for approval. However, the client rejects the plan saying it's unacceptable that the project will not deliver any value for 18 months. What is the best course of action for the project manager? (choose the best answer)
10The resource management plan calls for six developers to serve on the project team who are all internal employees. In the process of putting together the project team, the project manager discovers that only three developers with the necessary skillset are available for the project due to attrition and higher priority projects. What should the project manager do next? (choose the best answer)
11Project execution has just begun. As the project manager, you want to ensure the work is being performed according to the required quality standards. What is your best course of action? (choose the best answer)
12During video conferences, a project manager notices that a project team member frequently stands up and paces around the room while speaking. This behavior causes the team member to disappear from view and creates a distraction for the other meeting participants. What should the project manager do? (choose the best answer)
13At the sprint planning meeting, a project team works with the product owner to elaborate scope. After identifying themes, the meeting attendees define epics. However, the epics are too big to be developed within one sprint. The product owner suggests decomposing the epics into features. What should the team do to implement the product owner's suggestion? (choose the best answer)
14A project manager is monitoring the status of the project schedule for a product development project. The project deliverables are being produced in an iterative fashion, and the project has just completed seven of twelve planned sprints. The project manager has gathered the following information: 17 story points were completed and accepted in the seventh sprint 20 story points were planned for sprint #7 One feature worth 3 story points was completed but rejected and placed back in the product backlog The value of the features developed to date is $172,000 Actual costs to date are $167,000 The BAC for the project is $300,000 The project backlog contains 250 story points The project team has successfully completed 137 story points to date Which of the following accurately describes the schedule performance of the project for the seventh iteration? (choose the best answer)
15You are in the process of determining stakeholder needs and requirements for the project you are leading. There is a large number of stakeholders who are geographically dispersed, and you need their inputs quickly. What tool or technique would be the most effective in this situation? (choose the best answer)
16As a Scrum Master, you are facilitating a Sprint Planning, and you need to determine and bestow the appropriate level of decision making authority to the members of the Scrum Team. Which of the following activities are responsibilities of the Developers during this meeting? (Choose two.)
17As the team completes its third sprint, the company issues a new policy requiring each employee to report their work in the time tracking system. While the policy does not yet specify how detailed the records should be, the management encourages recording as many details as possible. The team members are unsure how to conform to this new policy. What recommendation should the project manager provide to the team? (choose the best answer)
18You are managing a four-phase project. The deliverables for the current phase have been accepted. What should you do before moving to the next phase? (choose the best answer)
19A Scrum Master is assigned to a new project in which ongoing stakeholder engagement will be a critical factor for the project's success. What strategy might the Scrum Master employ to monitor the satisfaction of key stakeholders? (choose the best answer)
20You meet with your team to determine the life cycle for your project. After analyzing the best way to define and manage requirements, develop deliverables, handle changes, control risk and cost, and engage key stakeholders, the decision is made to select a hybrid life cycle. With the project life cycle selected, how will the requirements be managed on your project? (choose the best answer)

Unanswered questions count as wrong.

How this test compares with the real CAPM exam

This free testReal CAPM examFull Exam Prep ($29)
Questions20150570
Time limitNone180 minutesMock Exam Mode: 180 minutes
Pass mark80% shown as a guideNot published by PMIScored against 80%
ExplanationsCorrect answers onlyNoneFor every question

See the CAPM exam guide for the full exam format, topics and how to book.

Questions about this practice test

Is this the real CAPM exam?

No. These are practice questions written by ScrumPrep in the style of the CAPM exam. The real exam is run by PMI, and its fee is paid to PMI separately.

What score should I aim for?

PMI does not publish a pass mark, so aim for 80% or more on full, timed mock exams before you book. A short untimed test like this one is easier than the real thing.

Do I need an account?

Not for this test. You only create a free account if you want the answer explanations in our free quiz, or if you buy the full Exam Prep.

How is the full CAPM Exam Prep different?

It has 570 questions with an explanation for each, a Practice Mode where you choose how many questions to take, and a Mock Exam Mode with 150 questions in 180 minutes, like the real exam. It costs $29 one time.

ScrumPrep is an independent exam prep provider. We are not affiliated with, endorsed by, or sponsored by the Project Management Institute (PMI), and all questions on this page are written by ScrumPrep and are not actual exam questions. PMI, PMP, CAPM and PMI-ACP are registered marks of the Project Management Institute, Inc.