Answering: “What is the primary purpose of the first part of the Nexus Sprint Retrospective, when representatives from across the Nexus meet?”

What is the primary purpose of the first part of the Nexus Sprint Retrospective, when representatives from across the Nexus meet?
(choose the best answer)
A. To identify the one item teams should discuss during their individual Sprint Retrospective.
B. To identify issues that impact multiple teams.
C. To discuss what went well during the Sprint.
D. To identify dependencies between teams.

Answering: “What is the primary purpose of the first part of the Nexus Sprint Retrospective, when representatives from across the Nexus meet?” Read More »

Answering: “From the below list, what factors should be most considered when establishing the length of a Sprint?”

From the below list, what factors should be most considered when establishing the length of a Sprint?
(choose the best two answers)
A. The frequency at which team formation can be changed.
B. All teams in a Nexus must have the same Sprint length.
C. The Nexus Integration Team determines the Sprint length for all teams in the Nexus.
D. The risk of being disconnected from the stakeholders.
E. The level of uncertainty over the technology to be used.

Answering: “From the below list, what factors should be most considered when establishing the length of a Sprint?” Read More »

Answering: “Select two ways in which leaving work undone at the end of the Sprint impacts transparency.”

Select two ways in which leaving work undone at the end of the Sprint impacts transparency.
(choose the best two answers)
A. The lack of transparency leads to false assumptions about the current state of the product.
B. As development progresses, the product becomes more difficult to integrate, which results in future work being slowed down in unpredictable ways.
C. When calculated and estimated, the total amount of undone work shows exactly how long until the Product Owner can release the Increment.
D. Undone work is acceptable as long as the Developers factor it into their future Sprint Plans.

Answering: “Select two ways in which leaving work undone at the end of the Sprint impacts transparency.” Read More »