Answering: “A six team Nexus is developing a full-featured e-commerce application. There are different parts of the application that only certain Scrum Teams can work on. In fact, there are some highly specialized individuals outside the Nexus that are required for some of the work. In past Sprints the Nexus encountered challenges dealing with the many dependencies between Scrum Teams. Which of the following practices could this Nexus try in order to conduct Nexus Sprint Planning more effectively?”
[color=#6495ed]Scenario B: Six Team Nexus with complex dependencies[/color]
A six team Nexus is developing a full-featured e-commerce application. There are different parts of the application that only certain Scrum Teams can work on. In fact, there are some highly specialized individuals outside the Nexus that are required for some of the work. In past Sprints the Nexus encountered challenges dealing with the many dependencies between Scrum Teams.
Which of the following practices could this Nexus try in order to conduct Nexus Sprint Planning more effectively?
(choose the best two answers)
A. Have the Nexus Integration Team select the work for each of the individual Scrum Teams. This allows the Nexus Integration Team to control the dependencies.
B. Visualize the known dependencies in the Product Backlog for all to see. As teams select work for the Sprint, they can easily check for any dependent work and communicate with other teams.
C. Plan one Scrum Team’s Sprint at a time before moving on to the next team. This way you can account for time zone differences and communicate dependencies across all teams.
D. Ensure all Scrum Teams and outside experts are available during the Nexus Sprint Planning event and have a way of quickly communicating with each other. They should try to be together in the same room or use technology that makes it seems as they are in the same room.