Answering: “Possible types of Product Backlog items include:”

Possible types of Product Backlog items include:
(choose the best answer)
A. Conducting a longitudinal study of customer behaviours.
B. Delivering a feature that requires lengthy customer interviews.
C. Running an experiment to test the viability of a proposed feature.
D. Conducting customer interviews to validate the outcomes of a previously released feature.
E. All of the above.

Answering: “Possible types of Product Backlog items include:” Read More »

Answering: “What happens if the Scrum Team cannot complete its work by the end of the Sprint?” (PSU I)

What happens if the Scrum Team cannot complete its work by the end of the Sprint?
(choose the best answer)
A. The Sprint is extended temporarily. Lessons are taken to ensure it doesn’t happen again.
B. The Sprint is extended and future Sprints use this new duration.
C. The Sprint length is unchanged and the Scrum Team continuously learns and adapts.

Answering: “What happens if the Scrum Team cannot complete its work by the end of the Sprint?” (PSU I) Read More »

Answering: “The Sprint Review is mainly an inspect and adapt opportunity for which group?” (PSU I)

The Sprint Review is mainly an inspect and adapt opportunity for which group?
(choose the best answer)
A. The Product Owner and the Developers.
B. The Product Owner and stakeholders.
C. The Product Owner and management.
D. The Scrum Team and stakeholders.
E. The Developers and management.
F. The Developers and stakeholders.

Answering: “The Sprint Review is mainly an inspect and adapt opportunity for which group?” (PSU I) Read More »