Answering: “True or False: Product documentation may be required as part of a working Increment.”
True or False: Product documentation may be required as part of a working Increment.
A. True
B. False
True or False: Product documentation may be required as part of a working Increment.
A. True
B. False
Who is responsible for a Sprint Backlog item that contains several database related tasks?
(choose the best answer)
A. Scrum Master.
B. Product Owner.
C. Project Stakeholders.
D. Developers.
E. Database administrator.
Which of the following are required by Scrum?
(choose all that apply)
A. Release burn-up.
B. Burn-down chart.
C. Unit tests.
D. Critical path analysis.
E. Refactoring.
F. Build automation.
G. None of the above.
Answering: “Which of the following are required by Scrum?” (PSD) Read More »
Which of the following best describe a ready Product Backlog item?
(choose the best two answers)
A. It is a complete user story with all its components.
B. It has been fully described in the requirements document.
C. It has been changed from unready to ready status in the tracking tool.
D. It can be most likely done within one Sprint.
E. It is well understood by the Developers and Product Owner at Sprint Planning.
Answering: “Which of the following best describe a ready Product Backlog item?” Read More »
True or False: Developers do not meet with stakeholders; only the Product Owner meets with stakeholders.
A. True
B. False
A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding she is accountable for the Product Backlog. However, she is unsure about her responsibilities. Which of the following are responsibilities of a Product Owner on a Scrum Team?
(choose the best two answers)
A. Interacting with stakeholders.
B. Creating detailed functional test cases.
C. Ensuring that the most valuable functionality is produced first.
D. Describing features as Use Cases.
E. Providing the Developers with detailed specifications.
You cannot copy content of this page