Answering: “You manage a product development organization. Some of your teams determine that they need access to a “production-like” test environment so that they can assess the scalability of their application as they build it. Current processes stipulate that expensive “production-like” test environments are only available as part of final application acceptance testing, just prior to releasing the application to production. Earlier access is not possible because other teams are using the pre-production test environments. Which two of the following strategies would you pursue?”

You manage a product development organization. Some of your teams determine that they need access to a “production-like” test environment so that they can assess the scalability of their application as they build it. Current processes stipulate that expensive “production-like” test environments are only available as part of final application acceptance testing, just prior to releasing the application to production. Earlier access is not possible because other teams are using the pre-production test environments. Which two of the following strategies would you pursue?
(choose the two best answers)
A. Tell the teams to do their best with their current test environment, simulating production as much as possible. Then release the product and let the customer determine if the product can scale.
B. You help them find someone who can help them with setting up testing and simulation software that can partially emulate the “production-like” test environment.
C. They should add additional time to the release schedule to account for the additional testing and rework the team will have to do when they find defects late in the delivery cycle. Set stakeholder expectations accordingly.
D. You work with the teams to develop a business case for procuring or gaining access to the necessary environment for validating the scalability of the product.

Answering: “You manage a product development organization. Some of your teams determine that they need access to a “production-like” test environment so that they can assess the scalability of their application as they build it. Current processes stipulate that expensive “production-like” test environments are only available as part of final application acceptance testing, just prior to releasing the application to production. Earlier access is not possible because other teams are using the pre-production test environments. Which two of the following strategies would you pursue?” Read More »

Answering: “You manage a product delivery organization. Your manager asks you to create a plan for the next fiscal year describing what will be delivered. What is the best way to proceed?”

You manage a product delivery organization. Your manager asks you to create a plan for the next fiscal year describing what will be delivered. What is the best way to proceed?
(choose the best answer)
A. Use your knowledge to make the plan and later negotiate its implementation with the Scrum Team.
B. Ask each Scrum Team to estimate the current backlog and make a plan against the story points previously delivered. Then normalize Story Points across teams to combine the estimates.
C. Work with specialists from each team to build an estimated backlog that you can translate into a Gantt chart.
D. Work with the Product Owner(s) to analyze current delivery capabilities against demand, then use that data to build a probabilistic forecast that serves to illustrate what might be achieved.

Answering: “You manage a product delivery organization. Your manager asks you to create a plan for the next fiscal year describing what will be delivered. What is the best way to proceed?” Read More »

Answering: “True or False: Lead Time is a measure of the time it takes to go from having an idea to the point where a customer experiences the benefit of that idea, and customer acceptance feedback has been gathered. This means that Lead Time is a way to measure business agility.”

True or False: Lead Time is a measure of the time it takes to go from having an idea to the point where a customer experiences the benefit of that idea, and customer acceptance feedback has been gathered. This means that Lead Time is a way to measure business agility.
A. True
B. False

Answering: “True or False: Lead Time is a measure of the time it takes to go from having an idea to the point where a customer experiences the benefit of that idea, and customer acceptance feedback has been gathered. This means that Lead Time is a way to measure business agility.” Read More »