Answering: “You are a Product Owner. The Developers are close to the end of a Sprint and asks you for 3 extra days to complete their work. They feel that if they do not get the extra time they might look bad in front of stakeholders, who are already skeptical of using an agile approach. What should you do?”
You are a Product Owner. The Developers are close to the end of a Sprint and asks you for 3 extra days to complete their work. They feel that if they do not get the extra time they might look bad in front of stakeholders, who are already skeptical of using an agile approach. What should you do?
(choose the best answer)
A. Ask the Developers to commit to what was agreed and find a solution for the problem.
B. Ask the Developers to work longer hours to meet their goal.
C. Cut back on testing, or leave some items incomplete, so long as the Developers can “substantially meet” their goal.
D. Agree to extend the Sprint but ask the team to be more realistic when they plan Sprints in the future.
E. Do not extend the Sprint and stick to the original time-box. Work with the stakeholders to explain why transparency and openness are important.