You facilitate a Sprint Retrospective and everyone seemed to leave the event satisfied. During Sprint Planning, a member of the Scrum Team says they do not think that the improvement item from the retrospective is important to work on, and a couple of other Scrum Team members nodded in agreement.
What do you think happened?
(choose the best answer)
A. The improvement action was not documented well enough.
B. The retrospective meeting went on for too long.
C. The retrospective was not facilitated in a way that enabled everyone to share their views and understand the views of others before a decision was made.
D. There was no manager in the retrospective to approve the improvement action.