Answering: “There are five Scrum Teams working on a Product. During the Nexus Sprint Review, the teams present the results of the Sprint. After introductions, each team takes time to present their work for inspection by individually showing the new features they have built. They are not using a shared environment. The stakeholders do not provide much feedback. The event ends and people filter out of the room. Since teams are not using a shared environment, what is likely?”

[color=#6495ed]Scenario A: Nexus Sprint Review with Five Scrum Teams[/color]
There are five Scrum Teams working on a Product. During the Nexus Sprint Review, the teams present the results of the Sprint. After introductions, each team takes time to present their work for inspection by individually showing the new features they have built. They are not using a shared environment. The stakeholders do not provide much feedback. The event ends and people filter out of the room.
Since teams are not using a shared environment, what is likely?
(choose the best two answers)
A. The Nexus has not yet reached the integration phase.
B. The Sprint is too short.
C. The Nexus Integration Team is lacking or nonexistent.
D. There is no single Integrated Increment.

Answering: “There are five Scrum Teams working on a Product. During the Nexus Sprint Review, the teams present the results of the Sprint. After introductions, each team takes time to present their work for inspection by individually showing the new features they have built. They are not using a shared environment. The stakeholders do not provide much feedback. The event ends and people filter out of the room. Since teams are not using a shared environment, what is likely?” Read More »

Answering: “If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?”

If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?
(choose the best answer)
A. Its productivity is likely to decrease.
B. Its productivity is likely to increase.
C. Its productivity is likely to stay the same.

Answering: “If two Scrum Teams are added to the development of a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?” Read More »

Answering: “Four teams in a Nexus typically integrate their work only once, late in the Sprint. The teams report that it takes many hours or days to integrate their work, which delays the Sprint’s end. To address this issue, which of the following would help?”

Four teams in a Nexus typically integrate their work only once, late in the Sprint. The teams report that it takes many hours or days to integrate their work, which delays the Sprint’s end. To address this issue, which of the following would help?
(choose the best answer)
A. Using Behavior-Driven Development.
B. Integrating more frequently.
C. Doing more exploratory testing.
D. Doing more acceptance testing.
E. Investing in more Requirements Traceability.
F. All of the above.

Answering: “Four teams in a Nexus typically integrate their work only once, late in the Sprint. The teams report that it takes many hours or days to integrate their work, which delays the Sprint’s end. To address this issue, which of the following would help?” Read More »

Answering: “Which list represents the most valuable items to discuss for a good Sprint Review agenda?”

Which list represents the most valuable items to discuss for a good Sprint Review agenda?
(choose the best answer)
A. Product Vision, Product Goal, Working Product Demo, Developer Status, Retrospective, Stakeholder Refinement.
B. Product Vision, Product Goal, Velocity, Working Product Demo, Budget Update.
C. Product Vision, Product Goal, Project Status, Velocity, Working Product Demo.
D. Product Vision, Product Goal, Sprint Goal, Working Product Demo, The Roadmap, Budget Update.

Answering: “Which list represents the most valuable items to discuss for a good Sprint Review agenda?” Read More »

Answering: “Which of the following is NOT a reason you should frequently evaluate who your stakeholders are and what level you should engage with them?”

Which of the following is NOT a reason you should frequently evaluate who your stakeholders are and what level you should engage with them?
(choose the best answer)
A. Frequent engagement with stakeholders fosters transparency.
B. Frequent stakeholder meetings are needed to keep the Product Backlog full.
C. The stakeholders obtaining value from the product may change over time.
D. Stakeholders hold valuable insights.

Answering: “Which of the following is NOT a reason you should frequently evaluate who your stakeholders are and what level you should engage with them?” Read More »

You cannot copy content of this page