Answering: “Which statements are true regarding using Scrum for large-scale product delivery?”

Which statements are true regarding using Scrum for large-scale product delivery?
(choose the best two answers)
A. Splitting a team member’s time between multiple Scrum Teams is often less productive than focusing that team member on a single team’s Sprint Backlog.
B. A well-structured and refined Product Backlog can minimize and often eliminate dependencies between multiple Scrum Teams working together on a product during a Sprint.
C. Scrum requires all team members work full time on a single team.
D. Changes to the core Scrum framework are needed to be successful with Scrum at large scale.

Answering: “Which statements are true regarding using Scrum for large-scale product delivery?” Read More »

Answering: “Select two ways in which leaving work undone at the end of the Sprint impacts transparency.”

Select two ways in which leaving work undone at the end of the Sprint impacts transparency.
(choose the best two answers)
A. The lack of transparency leads to false assumptions about the current state of the product.
B. As development progresses, the product becomes more difficult to integrate, which results in future work being slowed down in unpredictable ways.
C. When calculated and estimated, the total amount of undone work shows exactly how long until the Product Owner can release the Increment.
D. Undone work is acceptable as long as the Developers factor it into their future Sprint Plans.

Answering: “Select two ways in which leaving work undone at the end of the Sprint impacts transparency.” Read More »

Answering: “Currently, your Scrum Teams are organized to address a single layer only (for example, front end, middle tier, back end, and interfaces). What are three things to consider when deciding to move away from such component teams toward feature teams?”

Currently, your Scrum Teams are organized to address a single layer only (for example, front end, middle tier, back end, and interfaces). What are three things to consider when deciding to move away from such component teams toward feature teams?
(choose the best three answers)
A. With feature teams, it is easier to calculate the productivity per team.
B. Productivity may decrease when making this kind of move.
C. Feature teams have less communication overhead.
D. You cannot do Scrum without feature teams.
E. When making this change, it helps to have support from the organization.

Answering: “Currently, your Scrum Teams are organized to address a single layer only (for example, front end, middle tier, back end, and interfaces). What are three things to consider when deciding to move away from such component teams toward feature teams?” Read More »

Answering: “A six team Nexus is developing a full-featured e-commerce application. There are different parts of the application that only certain Scrum Teams can work on. In fact, there are some highly specialized individuals outside the Nexus that are required for some of the work. In past Sprints the Nexus encountered challenges dealing with the many dependencies between Scrum Teams. Some individual Scrum Teams in this Nexus have said that they do not see how the work they are doing is contributing to the product’s progress. What is the best remedy for this situation?”

[color=#6495ed]Scenario B: Six Team Nexus with complex dependencies[/color]
A six team Nexus is developing a full-featured e-commerce application. There are different parts of the application that only certain Scrum Teams can work on. In fact, there are some highly specialized individuals outside the Nexus that are required for some of the work. In past Sprints the Nexus encountered challenges dealing with the many dependencies between Scrum Teams.
Some individual Scrum Teams in this Nexus have said that they do not see how the work they are doing is contributing to the product’s progress. What is the best remedy for this situation?
(choose the best answer)
A. Ask the Scrum Master to explain to the teams that the Product Owner can choose which features to work on, as she has the final say.
B. During Nexus Sprint Planning, have all the teams plan the Sprint together in one room, so they can see what other teams are working on.
C. During Nexus Sprint Planning, ensure that all Scrum Teams understand the Nexus Sprint Goal.
D. During Nexus Sprint Planning, ask each Scrum Team to create a Sprint Goal that describes the purpose of the Sprint.

Answering: “A six team Nexus is developing a full-featured e-commerce application. There are different parts of the application that only certain Scrum Teams can work on. In fact, there are some highly specialized individuals outside the Nexus that are required for some of the work. In past Sprints the Nexus encountered challenges dealing with the many dependencies between Scrum Teams. Some individual Scrum Teams in this Nexus have said that they do not see how the work they are doing is contributing to the product’s progress. What is the best remedy for this situation?” Read More »

Answering: “How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?”

How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?
(choose the best answer)
A. The Developers pull work in agreement with the Product Owner.
B. The Scrum Teams choose the Weighted Shorted Job First.
C. The Product Owner should provide each team with its own Product Backlog.
D. The Scrum Team with the highest velocity pulls Product Backlog items first.
E. Each Scrum Team takes an equal number of items.

Answering: “How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?” Read More »